# 145 Albion St

Block 3568, lot 068. Page: https://www.permitgraph.org/a/3568/068

The city's assessor roll has no record for this parcel.

## Permits filed here

35 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [M493107](https://www.permitgraph.org/p/M493107) | Jun 4, 2014 | Never finaled: issued Jun 2014, no final | [145 Albion St](https://www.permitgraph.org/a/3568/068) |  | street space |  |
| [201402289599](https://www.permitgraph.org/p/201402289599) | Feb 28, 2014 | Completed: final sign-off Aug 2014 | [149 Albion St](https://www.permitgraph.org/a/3568/068) | [Jim Parr Dba Plumbing](https://www.permitgraph.org/contractor/jim-parr-dba-plumbing-529553) | submit as built drawing to app#201212105850 |  |
| [201310290512](https://www.permitgraph.org/p/201310290512) | Oct 29, 2013 | Completed: final sign-off Aug 2014 | [145 Albion St](https://www.permitgraph.org/a/3568/068) | [International Fire Inc](https://www.permitgraph.org/contractor/international-fire-inc-965370) | new fire alarm system:install new panel in the garage, smoke detector above & pull station near. install notification devices thru out floor areas. | $5,400 |
| [201310038439](https://www.permitgraph.org/p/201310038439) | Oct 3, 2013 | Expired or cancelled: expired Mar 2016 | [149 Albion St](https://www.permitgraph.org/a/3568/068) | [Van Der Sterre Construction](https://www.permitgraph.org/contractor/van-der-sterre-construction-456718) | new 3-stop residential dumbwaiter & shaft. and replace extg drivway slab and extg vehicular gate with new driveway slab and new vehicular gate in like kind. new half bath new hot tub, new skylight, g… | $3,600 |
| [201308235098](https://www.permitgraph.org/p/201308235098) | Aug 23, 2013 | Never finaled: issued Oct 2013, no final | [149 Albion St](https://www.permitgraph.org/a/3568/068) | [Schmitt Heating Co Inc](https://www.permitgraph.org/contractor/schmitt-heating-co-inc-708941) | install new roof top gas and electric package unit. install new flexible ducting with new steel risers. | $16,400 |
| [M416367](https://www.permitgraph.org/p/M416367) | Aug 13, 2013 | Never finaled: issued Aug 2013, no final | [145 Albion St](https://www.permitgraph.org/a/3568/068) |  | street space |  |
| [M369867](https://www.permitgraph.org/p/M369867) | Feb 5, 2013 | Never finaled: issued Feb 2013, no final | [145 Albion St](https://www.permitgraph.org/a/3568/068) |  | street space permit |  |
| [201212105850](https://www.permitgraph.org/p/201212105850) | Dec 10, 2012 | Never finaled: issued Dec 2012, no final | [145 Albion St](https://www.permitgraph.org/a/3568/068) | [Jim Parr Dba Plumbing](https://www.permitgraph.org/contractor/jim-parr-dba-plumbing-529553) | install fire sprinkler system (nfpa 13) as per plan with 96 sprinkler heads, includes underground service. per pa #2010-0604-3843. | $38,500 |
| [201208036480](https://www.permitgraph.org/p/201208036480) | Aug 3, 2012 | Never finaled: issued Aug 2012, no final | [149 Albion St](https://www.permitgraph.org/a/3568/068) | [Van Der Sterre Construction](https://www.permitgraph.org/contractor/van-der-sterre-construction-456718) | underpin & brace existing foundation per plan neighbors. bracing to utilize new mat slba (partial) of new bldg -under approved pa# 201006043843. | $2,500 |
| [M340108](https://www.permitgraph.org/p/M340108) | Aug 3, 2012 | Never finaled: issued Aug 2012, no final | [145 Albion St](https://www.permitgraph.org/a/3568/068) |  | street space |  |
| [M223690](https://www.permitgraph.org/p/M223690) | Oct 5, 2010 | Never finaled: issued Oct 2010, no final | [145 Albion St](https://www.permitgraph.org/a/3568/068) |  | administrative permit to memorialize assign addresses in 2004. |  |
| [201006043843](https://www.permitgraph.org/p/201006043843) | Jun 4, 2010 | Completed: final sign-off Jan 2015 | [149 Albion St](https://www.permitgraph.org/a/3568/068) |  | to erect 3 units, 4 stories residential building. | $700,000 |
| [201006043841](https://www.permitgraph.org/p/201006043841) | Jun 4, 2010 | Completed: final sign-off Jun 2015 | [149 Albion St](https://www.permitgraph.org/a/3568/068) |  | to demolish 1 story shed. | $3,000 |
| [200904095974](https://www.permitgraph.org/p/200904095974) | Apr 9, 2009 | Completed: final sign-off Aug 2009 | [141 Albion St](https://www.permitgraph.org/a/3568/068) |  | revision to 200708018483. remove garage doors, rebuild front gate and fence. modify ground floor layout, eliminate unused fixtures. add 2 skylights. 1st floor living area change from storage, elimina… | $2,000 |
| [200903093604](https://www.permitgraph.org/p/200903093604) | Mar 9, 2009 | Never finaled: issued Mar 2009, no final | [145 Albion St](https://www.permitgraph.org/a/3568/068) |  | to obtain inspection for work approved under pa#200409164340. all work has been completed. |  |
| [200903093606](https://www.permitgraph.org/p/200903093606) | Mar 9, 2009 | Expired or cancelled: cancelled Aug 2022 | [141 Albion St](https://www.permitgraph.org/a/3568/068) |  | to obtain inspection for work approved under pa#200708018483. all work has been completed. |  |
| [200903093616](https://www.permitgraph.org/p/200903093616) | Mar 9, 2009 | Completed: final sign-off Aug 2009 | [141 Albion St](https://www.permitgraph.org/a/3568/068) |  | to obtain final inspection for work approved under pa#200708018483. all work has been completed. |  |
| [200903093607](https://www.permitgraph.org/p/200903093607) | Mar 9, 2009 | Completed: final sign-off Aug 2009 | [141 Albion St](https://www.permitgraph.org/a/3568/068) |  | to obtain inspection for work approved under pa#200308202611. all work has been completed. |  |
| [200903093634](https://www.permitgraph.org/p/200903093634) | Mar 9, 2009 | Expired or cancelled: cancelled Aug 2022 | [145 Albion St](https://www.permitgraph.org/a/3568/068) |  | driveway gate and construction gates installed(no driveway cut). see complaint 200986460 | $500 |
| [200903093603](https://www.permitgraph.org/p/200903093603) | Mar 9, 2009 | Never finaled: issued Mar 2009, no final | [145 Albion St](https://www.permitgraph.org/a/3568/068) |  | to obtain inspection for work approved under pa#200310278660. all work has been completed. |  |
| [200903093605](https://www.permitgraph.org/p/200903093605) | Mar 9, 2009 | Completed: final sign-off Aug 2009 | [141 Albion St](https://www.permitgraph.org/a/3568/068) |  | to obtain inspection for work approved under pa#200612079431. all work has been completed. |  |
| [200812198845](https://www.permitgraph.org/p/200812198845) | Dec 19, 2008 | Completed: final sign-off Sep 2009 | [141 Albion St](https://www.permitgraph.org/a/3568/068) |  | remove two steel columns and cut two steel beams at garage, add 2 columns at garage. seismic strenghtening work was completed under permit application 2003-08-20-2611 | $4,000 |
| [M137027](https://www.permitgraph.org/p/M137027) | Oct 14, 2008 | Never finaled: issued Oct 2008, no final | [141 Albion St](https://www.permitgraph.org/a/3568/068) |  | street space permit |  |
| [200711208657](https://www.permitgraph.org/p/200711208657) | Nov 20, 2007 | Completed: final sign-off Aug 2009 | [141 Albion St](https://www.permitgraph.org/a/3568/068) | [F P U Inc](https://www.permitgraph.org/contractor/f-p-u-inc-747811) | installation of automatic fire sprinklers system 13d- 13r (unit 141-145 ) | $40,000 |
| [M87884](https://www.permitgraph.org/p/M87884) | Sep 25, 2007 | Never finaled: issued Sep 2007, no final | [141 Albion St](https://www.permitgraph.org/a/3568/068) |  | streetspace and sidewalk |  |
| [200708018483](https://www.permitgraph.org/p/200708018483) | Aug 1, 2007 | Completed: final sign-off Aug 2009 | [141 Albion St](https://www.permitgraph.org/a/3568/068) |  | revisions to app # 200612079431 and #200308202611/s.as built condition that add a 1/2 bath to unit 2 at 1/fl and full bath to mezz level.this app also corrects the exist unit count as 2 units new cit… | $10,000 |
| [200612079431](https://www.permitgraph.org/p/200612079431) | Dec 7, 2006 | Expired or cancelled: expired Aug 2009 | [141 Albion St](https://www.permitgraph.org/a/3568/068) |  | rev. of foundation/structural design at basement/groundfloor as per #2003/08/20/2611s1r5 reconfiguration of groundfloor/basement level. (all other work as per original permit) |  |
| [M34024](https://www.permitgraph.org/p/M34024) | Aug 25, 2005 | Never finaled: issued Aug 2005, no final | [141 Albion St](https://www.permitgraph.org/a/3568/068) |  | sidewalk repair |  |
| [M29474](https://www.permitgraph.org/p/M29474) | Sep 28, 2004 | Never finaled: issued Sep 2004, no final | [149 Albion St](https://www.permitgraph.org/a/3568/068) |  | address assignment |  |
| [M29473](https://www.permitgraph.org/p/M29473) | Sep 28, 2004 | Never finaled: issued Sep 2004, no final | [149 Albion St](https://www.permitgraph.org/a/3568/068) |  | address assignment |  |
| [M29472](https://www.permitgraph.org/p/M29472) | Sep 28, 2004 | Never finaled: issued Sep 2004, no final | [147 Albion St](https://www.permitgraph.org/a/3568/068) |  | address assignment |  |
| [M29471](https://www.permitgraph.org/p/M29471) | Sep 28, 2004 | Never finaled: issued Sep 2004, no final | [145 Albion St](https://www.permitgraph.org/a/3568/068) |  | address assignment |  |
| [200409164340](https://www.permitgraph.org/p/200409164340) | Sep 16, 2004 | Expired or cancelled: expired May 2006 | [145 Albion St](https://www.permitgraph.org/a/3568/068) |  | remove porch @ side of (e)res. due to dry rot.no replacement proposed & future work covered under | $500 |
| [200310278660](https://www.permitgraph.org/p/200310278660) | Oct 27, 2003 | Expired or cancelled: expired Mar 2005 | [145 Albion St](https://www.permitgraph.org/a/3568/068) |  | remove fixed glass panel&frame to exterior courtyard. is addition work to remedy illegal apt units. | $500 |
| [200308202611](https://www.permitgraph.org/p/200308202611) | Aug 20, 2003 | Expired or cancelled: expired Jan 2009 | [141 Albion St](https://www.permitgraph.org/a/3568/068) |  | remove/abate 2 illegal apartments. add to (e) structure. create new 5 car parking gargage @ basement, with 2 & 3 story addition. convert portion of (e) structure into 2 seperate units. add new mezz f… | $750,000 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Jim Parr Dba Plumbing](https://www.permitgraph.org/contractor/jim-parr-dba-plumbing-529553) (2), [Van Der Sterre Construction](https://www.permitgraph.org/contractor/van-der-sterre-construction-456718) (2), [F P U Inc](https://www.permitgraph.org/contractor/f-p-u-inc-747811), [International Fire Inc](https://www.permitgraph.org/contractor/international-fire-inc-965370), [Schmitt Heating Co Inc](https://www.permitgraph.org/contractor/schmitt-heating-co-inc-708941)
- Architects: [Owen Kennerly](https://www.permitgraph.org/professional/owen-kennerly-C29565) (2)
- Engineers: [David Strandberg](https://www.permitgraph.org/professional/david-strandberg-62993)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.