# 164 14th St

Block 3530, lot 049. Page: https://www.permitgraph.org/a/3530/049

- City's use: Industrial
- Built: 1923
- Stories: 2
- Units: 1
- Rooms: 2 bathrooms
- Building: 10,035 sq ft
- Lot: 9,120 sq ft
- Zoning: M1
- Construction type: D

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

7 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [202605040566](https://www.permitgraph.org/p/202605040566) | May 4, 2026 | In progress: filed May 2026, not yet issued | [164 14th St](https://www.permitgraph.org/a/3530/049) |  | to comply with nov 202046581 - fire damage replacement in-kind replace 2 teel beams; replace exterior metal siding of north wall | $24,000 |
| [M577587](https://www.permitgraph.org/p/M577587) | Apr 14, 2015 | Never finaled: issued Apr 2015, no final | [160 14th St](https://www.permitgraph.org/a/3530/049) |  | street space permit |  |
| [201503251907](https://www.permitgraph.org/p/201503251907) | Mar 25, 2015 | Completed: final sign-off Jul 2016 | [160 14th St](https://www.permitgraph.org/a/3530/049) | [Tritone Construction](https://www.permitgraph.org/contractor/tritone-construction-872565) | removed window sill to repair dry rot and found additional rot. removed stucco and sheathing to access framing found rot issues with framing and repair replaced as needed. repair front approx 20'x 8'… | $4,000 |
| [201402279457](https://www.permitgraph.org/p/201402279457) | Feb 27, 2014 | Completed: final sign-off Feb 2016 | [160 14th St](https://www.permitgraph.org/a/3530/049) |  | to obtain final inspection for work approved under app#200710034503. all work is complete. |  |
| [201402077995](https://www.permitgraph.org/p/201402077995) | Feb 7, 2014 | Completed: final sign-off Feb 2016 | [160 14th St](https://www.permitgraph.org/a/3530/049) | [International Fire Equip](https://www.permitgraph.org/contractor/international-fire-equip-253912) | upgrade fire system to ul 300 | $2,500 |
| [200710034503](https://www.permitgraph.org/p/200710034503) | Oct 3, 2007 | Completed: final sign-off Feb 2016 | [160 14th St](https://www.permitgraph.org/a/3530/049) |  | change of occupancy at 2nd floor to r-3/ provide 1 hour separation between new dwelling unit and existing office space. new vestibule at 1st floor. | $50,000 |
| [200702083685](https://www.permitgraph.org/p/200702083685) | Feb 8, 2007 | Expired or cancelled: expired May 2009 | [160 14th St](https://www.permitgraph.org/a/3530/049) | [Aquamatic Fire Protection](https://www.permitgraph.org/contractor/aquamatic-fire-protection-669521) | add 3 sprinklers in new cooler boxes, relocate 6 due to tenant improvement. add 6 due to tenant improvement ti interior. | $5,000 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Aquamatic Fire Protection](https://www.permitgraph.org/contractor/aquamatic-fire-protection-669521), [International Fire Equip](https://www.permitgraph.org/contractor/international-fire-equip-253912), [Tritone Construction](https://www.permitgraph.org/contractor/tritone-construction-872565)
- Architects: [Peter Petruzzi](https://www.permitgraph.org/professional/peter-petruzzi-C18480)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/a/3530/049.