# 650 Lake St

Block 1351, lot 022. Page: https://www.permitgraph.org/a/1351/022

- City's use: Multi-Family Residential
- Built: 1963
- Stories: 3
- Units: 12
- Rooms: 18 bathrooms
- Building: 10,881 sq ft
- Lot: 4,392 sq ft
- Zoning: RM2
- Construction type: D

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

11 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [202406174620](https://www.permitgraph.org/p/202406174620) | Jun 17, 2024 | Completed: final sign-off Sep 2024 | [650 Lake St](https://www.permitgraph.org/a/1351/022) | [Yong Hong Construction Inc.](https://www.permitgraph.org/contractor/yong-hong-construction-inc-855109) | bathroom remodel for unit# 7 and #11. replace bathtub with shower pan and replace tile. replace kitchen cabinets and countertop only for unit# 11. | $26,500 |
| [202402286774](https://www.permitgraph.org/p/202402286774) | Feb 28, 2024 | Completed: final sign-off Mar 2025 | [650 Lake St](https://www.permitgraph.org/a/1351/022) | [Commercial Fire Protection Llc](https://www.permitgraph.org/contractor/commercial-fire-protection-llc-1090996) | upgrade (e) fire alarm devices to be replced to including manual pull stations and smoke detctors. (e) bells to be repl with horn/strobes & strobes. units to have 520hz low freq audibiles installed.f… | $31,000 |
| [202304135648](https://www.permitgraph.org/p/202304135648) | Apr 13, 2023 | Completed: final sign-off Aug 2023 | [650 Lake St](https://www.permitgraph.org/a/1351/022) | [Yong Hong Construction Inc.](https://www.permitgraph.org/contractor/yong-hong-construction-inc-855109) | remove stucco and replace stucco like for like. one side of bldg. approx 600sf | $8,000 |
| [M1162827](https://www.permitgraph.org/p/M1162827) | Nov 6, 2019 | Never finaled: issued Nov 2019, no final | [650 Lake St](https://www.permitgraph.org/a/1351/022) |  | street space |  |
| [201910305937](https://www.permitgraph.org/p/201910305937) | Oct 30, 2019 | Completed: final sign-off Jan 2020 | [650 Lake St](https://www.permitgraph.org/a/1351/022) | [Yong Hong Construction Inc.](https://www.permitgraph.org/contractor/yong-hong-construction-inc-855109) | supply & install 17 iwc aluminum windows & 16 iwc aluminum doors to match (e) design, double-pane, same size and same location | $105,000 |
| [201908209308](https://www.permitgraph.org/p/201908209308) | Aug 20, 2019 | Completed: final sign-off Jan 2020 | [650 Lake St](https://www.permitgraph.org/a/1351/022) | [Yong Hong Construction Inc.](https://www.permitgraph.org/contractor/yong-hong-construction-inc-855109) | unit #4 only, remove and replace three sliding doors and four windows in kind, in same openings. repair stucco around windows/doors only as needed. new windows and doors to be aluminum, as are existi… | $18,500 |
| [201609289067](https://www.permitgraph.org/p/201609289067) | Sep 28, 2016 | Completed: final sign-off May 2018 | [650 Lake St](https://www.permitgraph.org/a/1351/022) | [Allied Teamwork Construction Co](https://www.permitgraph.org/contractor/allied-teamwork-construction-co-865282) | soft story retrofit per sfbc chapter 34b engineering criteria. 2012 iebc appendix a-4 | $75,000 |
| [201111158927](https://www.permitgraph.org/p/201111158927) | Nov 15, 2011 | Never finaled: issued Nov 2011, no final | [650 Lake St](https://www.permitgraph.org/a/1351/022) | [Yong Hong Construction Inc.](https://www.permitgraph.org/contractor/yong-hong-construction-inc-855109) | three (3) windoww and three (3) doors replacement at front with double pan alumunum frame. replace in kind glass sliding door. no change in egress and no structural work - u factor = 0.40 max | $5,600 |
| [201109235326](https://www.permitgraph.org/p/201109235326) | Sep 23, 2011 | Never finaled: issued Sep 2011, no final | [650 Lake St](https://www.permitgraph.org/a/1351/022) | [All Four Season's Roofing](https://www.permitgraph.org/contractor/all-four-season-s-roofing-769155) | reroofing | $8,000 |
| [201005041663](https://www.permitgraph.org/p/201005041663) | May 4, 2010 | Completed: final sign-off Jun 2010 | [650 Lake St](https://www.permitgraph.org/a/1351/022) | [Yong Hong Construction Inc.](https://www.permitgraph.org/contractor/yong-hong-construction-inc-855109) | 6 windows replacement at front with double pan aluminum frame. | $3,000 |
| [200805192409](https://www.permitgraph.org/p/200805192409) | May 19, 2008 | Completed: final sign-off Sep 2008 | [650 Lake St](https://www.permitgraph.org/a/1351/022) | [Yong Hong Construction Inc.](https://www.permitgraph.org/contractor/yong-hong-construction-inc-855109) | 10 window replacement | $8,500 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Yong Hong Construction Inc.](https://www.permitgraph.org/contractor/yong-hong-construction-inc-855109) (7), [All Four Season's Roofing](https://www.permitgraph.org/contractor/all-four-season-s-roofing-769155), [Allied Teamwork Construction Co](https://www.permitgraph.org/contractor/allied-teamwork-construction-co-865282), [Commercial Fire Protection Llc](https://www.permitgraph.org/contractor/commercial-fire-protection-llc-1090996)
- Engineers: [Darren Wong](https://www.permitgraph.org/professional/darren-wong-C81082)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 23 November 2026.