# 661 Divisadero St

Block 1201, lot 001. Page: https://www.permitgraph.org/a/1201/001

- City's use: Commercial Retail
- Built: 1915
- Stories: 1
- Building: 3,964 sq ft
- Lot: 3,791 sq ft
- Zoning: NC2
- Construction type: NA

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

23 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [202504043783](https://www.permitgraph.org/p/202504043783) | Apr 4, 2025 | In progress: issued Apr 2025 | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) | [Fireside Security Dba Access Cabling](https://www.permitgraph.org/contractor/fireside-security-dba-access-cabling-992009) | replace smoke detector over facp with heat detector due to nuisance alarms | $2,000 |
| [201801088091](https://www.permitgraph.org/p/201801088091) | Jan 8, 2018 | Completed: final sign-off Apr 2018 | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) | [Team Commercial Construction Inc.](https://www.permitgraph.org/contractor/team-commercial-construction-inc-735561) | revision to pa 2017-1113-3831 revision for barrier removal at secondary egress door. provide ada compliant door landing and add automatic door opener (interior); n/a maher | $9,000 |
| [201711214572](https://www.permitgraph.org/p/201711214572) | Nov 21, 2017 | Completed: final sign-off Apr 2018 | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) | [Team Commercial Construction Inc.](https://www.permitgraph.org/contractor/team-commercial-construction-inc-735561) | revision to 201709056928 - change to 6.0 dgt 4 window change. to rectify violation #201719681 & 201714882. maher na. |  |
| [M857567](https://www.permitgraph.org/p/M857567) | Nov 20, 2017 | Never finaled: issued Nov 2017, no final | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) |  | street space permit |  |
| [201711133831](https://www.permitgraph.org/p/201711133831) | Nov 13, 2017 | Completed: final sign-off Apr 2018 | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) | [Team Commercial Construction Inc.](https://www.permitgraph.org/contractor/team-commercial-construction-inc-735561) | administrative preservation review only of previously approved bpa 201709056928, (n) windows will be fixed and curb cut will be removed to comply with complaint 201714882 |  |
| [M841147](https://www.permitgraph.org/p/M841147) | Oct 10, 2017 | Never finaled: issued Oct 2017, no final | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) |  | street space w/mta |  |
| [201709056928](https://www.permitgraph.org/p/201709056928) | Sep 5, 2017 | Completed: final sign-off Apr 2018 | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) | [Team Commercial Construction Inc.](https://www.permitgraph.org/contractor/team-commercial-construction-inc-735561) | tenant improvements to existing storefront. demo existing rolling garaged doors used as windows w/new wood window system. windows fixed & non-operable. n/a for maher | $45,000 |
| [201509157039](https://www.permitgraph.org/p/201509157039) | Sep 15, 2015 | Never finaled: issued Dec 2015, no final | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) | [Del Rey Construction Inc](https://www.permitgraph.org/contractor/del-rey-construction-inc-412533) | interior improvement - install new service counter/bar w/new equipment, new conter & new pass thru window per health dept requirements. no chagne to lighting or hvac. modify e garage doors. remove cu… | $12,000 |
| [201307091356](https://www.permitgraph.org/p/201307091356) | Jul 9, 2013 | Completed: final sign-off Aug 2013 | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) | [International Fire Equip](https://www.permitgraph.org/contractor/international-fire-equip-253912) | installation of ul300 fire system, ref #201211154351 | $3,000 |
| [M403667](https://www.permitgraph.org/p/M403667) | Jun 25, 2013 | Never finaled: issued Jun 2013, no final | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) |  | street space |  |
| [201306119144](https://www.permitgraph.org/p/201306119144) | Jun 11, 2013 | Completed: final sign-off Aug 2013 | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) | [K K Electric & Alarm Company](https://www.permitgraph.org/contractor/k-k-electric-alarm-company-893093) | install fire alarm system. 2 intiating & 12 notification. | $3,800 |
| [201306058784](https://www.permitgraph.org/p/201306058784) | Jun 5, 2013 | Completed: final sign-off Sep 2013 | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) | [Del Rey Construction Inc](https://www.permitgraph.org/contractor/del-rey-construction-inc-412533) | revision to appl #2012.11.15.4351-s: install fire sprinkler system, add one accessible unisex restroom, eliminate one exterior door & replace with window. fire sprinkler under separate permit. | $40,000 |
| [201305156947](https://www.permitgraph.org/p/201305156947) | May 15, 2013 | Completed: final sign-off Aug 2013 | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) | [Fong's Construction & Plumbing](https://www.permitgraph.org/contractor/fong-s-construction-plumbing-499286) | install new fire spirnkler system throughout building including new fire service, total 75 heads, ref pa #2012.11.15.4351 | $37,500 |
| [201305076319](https://www.permitgraph.org/p/201305076319) | May 7, 2013 | Completed: final sign-off Sep 2013 | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) | [Del Rey Construction Inc](https://www.permitgraph.org/contractor/del-rey-construction-inc-412533) | add framing to (e) wood frame roof on the one story section of the building additional work to pa201211154351 | $12,000 |
| [M386167](https://www.permitgraph.org/p/M386167) | Apr 17, 2013 | Never finaled: issued Apr 2013, no final | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) |  | street space |  |
| [201303192474](https://www.permitgraph.org/p/201303192474) | Mar 19, 2013 | Never finaled: issued Mar 2013, no final | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) | [Del Rey Construction Inc](https://www.permitgraph.org/contractor/del-rey-construction-inc-412533) | non-structural interior demolition of certain partitions and an area of cracked concrete floor slab. no change to mechanical system. | $3,000 |
| [201211154351](https://www.permitgraph.org/p/201211154351) | Nov 15, 2012 | Completed: final sign-off Sep 2013 | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) | [Del Rey Construction Inc](https://www.permitgraph.org/contractor/del-rey-construction-inc-412533) | application for a312 mailing for a change of use with the planning dept. building permit plans will be submitted as an addendum. | $50,000 |
| [M130890](https://www.permitgraph.org/p/M130890) | Aug 15, 2008 | Never finaled: issued Aug 2008, no final | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) |  | street space permit |  |
| [200804210206](https://www.permitgraph.org/p/200804210206) | Apr 21, 2008 | Completed: final sign-off Oct 2008 | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) | [Cove Construction](https://www.permitgraph.org/contractor/cove-construction-705773) | revision to pa# 2008-0308-7393-install new foundation | $7,000 |
| [M114188](https://www.permitgraph.org/p/M114188) | Mar 27, 2008 | Never finaled: issued Mar 2008, no final | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) |  | street space & sidewalk permit only. |  |
| [200803187393](https://www.permitgraph.org/p/200803187393) | Mar 18, 2008 | Completed: final sign-off Nov 2008 | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) |  | new skylights (dome),handicap upgrades to include bathroom, entry, new storage room, handrail at stair on 1st floor. new windows, new lights, new shear wall on 2nd floor. remove front bars & gate. | $94,500 |
| [M48005](https://www.permitgraph.org/p/M48005) | Nov 9, 2006 | Never finaled: issued Nov 2006, no final | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) |  | street space & sidewalk repair |  |
| [200510286838](https://www.permitgraph.org/p/200510286838) | Oct 28, 2005 | Completed: final sign-off Nov 2005 | [661 Divisadero St](https://www.permitgraph.org/a/1201/001) |  | reroofing | $3,000 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Del Rey Construction Inc](https://www.permitgraph.org/contractor/del-rey-construction-inc-412533) (5), [Team Commercial Construction Inc.](https://www.permitgraph.org/contractor/team-commercial-construction-inc-735561) (4), [Cove Construction](https://www.permitgraph.org/contractor/cove-construction-705773), [Fireside Security Dba Access Cabling](https://www.permitgraph.org/contractor/fireside-security-dba-access-cabling-992009), [Fong's Construction & Plumbing](https://www.permitgraph.org/contractor/fong-s-construction-plumbing-499286), [International Fire Equip](https://www.permitgraph.org/contractor/international-fire-equip-253912), [K K Electric & Alarm Company](https://www.permitgraph.org/contractor/k-k-electric-alarm-company-893093)
- Architects: [Janet Crane](https://www.permitgraph.org/professional/janet-crane-C8295) (3), [Max A Crome](https://www.permitgraph.org/professional/max-a-crome-C25487) (3), [Christopher Sullivan](https://www.permitgraph.org/professional/christopher-sullivan-C30234), [Lisa Harvey](https://www.permitgraph.org/professional/lisa-harvey-C23004)
- Engineers: [Sedco](https://www.permitgraph.org/professional/sedco-57642)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/a/1201/001.