# 2120 Golden Gate Av

Block 1149, lot 010. Page: https://www.permitgraph.org/a/1149/010

The city's assessor roll has no record for this parcel.

## Permits filed here

5 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [202104299584](https://www.permitgraph.org/p/202104299584) | Apr 29, 2021 | Completed: final sign-off Aug 2021 | [2120 Golden Gate Av](https://www.permitgraph.org/a/1149/010) | [Convergint Technologies Llc](https://www.permitgraph.org/contractor/convergint-technologies-llc-986407) | install new gst i064 fire alarm control unit on first floor for monitoring of the fire sprinkler system; 1-manual pull station, 5-monitor modules, 1-smoke detector, 1-cellular communicator |  |
| [202009103905](https://www.permitgraph.org/p/202009103905) | Sep 10, 2020 | Completed: final sign-off Oct 2021 | [2120 Golden Gate Av](https://www.permitgraph.org/a/1149/010) | [Herrero Builders Incorporated](https://www.permitgraph.org/contractor/herrero-builders-incorporated-152980) | deferred mep for pa# 201911258136 | $10,000 |
| [202009043526](https://www.permitgraph.org/p/202009043526) | Sep 4, 2020 | Completed: final sign-off Aug 2021 | [2120 Golden Gate Av](https://www.permitgraph.org/a/1149/010) | [Potter Fire Protection](https://www.permitgraph.org/contractor/potter-fire-protection-338830) | new sprinkler waterflow and supervisory system. ref pa# 201911258136 | $2,000 |
| [202009023292](https://www.permitgraph.org/p/202009023292) | Sep 2, 2020 | Completed: final sign-off Aug 2021 | [2120 Golden Gate Av](https://www.permitgraph.org/a/1149/010) | [Potter Fire Protection](https://www.permitgraph.org/contractor/potter-fire-protection-338830) | fire sprinkler system for work under bpa#201911258136 | $15,000 |
| [201911258136](https://www.permitgraph.org/p/201911258136) | Nov 25, 2019 | Completed: final sign-off Oct 2021 | [2120 Golden Gate Av](https://www.permitgraph.org/a/1149/010) | [Herrero Builders Incorporated](https://www.permitgraph.org/contractor/herrero-builders-incorporated-152980) | convert (e)2 residential units to 4 units. no change to building height, mep and fire sprinklers deferred. associated with building permit #201910164593 and cua #2018002179 | $325,000 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Herrero Builders Incorporated](https://www.permitgraph.org/contractor/herrero-builders-incorporated-152980) (2), [Potter Fire Protection](https://www.permitgraph.org/contractor/potter-fire-protection-338830) (2), [Convergint Technologies Llc](https://www.permitgraph.org/contractor/convergint-technologies-llc-986407)
- Architects: [Laura Rambin](https://www.permitgraph.org/professional/laura-rambin-C27742) (2)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.