# 2350 Geary Blvd

Block 1080, lot 034. Page: https://www.permitgraph.org/a/1080/034

- City's use: Commercial Office
- Built: 1927
- Stories: 3
- Building: 24,351 sq ft
- Lot: 23,091 sq ft
- Zoning: RH3
- Construction type: D

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

31 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [202406073980](https://www.permitgraph.org/p/202406073980) | Jun 14, 2024 | Completed: final sign-off Jul 2026 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [W. Bradley Electric](https://www.permitgraph.org/contractor/w-bradley-electric-1114449), [Turner Construction Co](https://www.permitgraph.org/contractor/turner-construction-co-210639) | fire alarm system migration @ the kaiser(cn31-03)medical office bldg;migrant to (n) equipment, 1 control panel,11 pull stations, 7 modules,75 smoke detectors,15 heat detectors,43 strobes,12 chime/str… | $1,345,515 |
| [M420327](https://www.permitgraph.org/p/M420327) | Aug 23, 2013 | Never finaled: issued Aug 2013, no final | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | street space |  |
| [201209240437](https://www.permitgraph.org/p/201209240437) | Sep 24, 2012 | Completed: final sign-off May 2014 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Ad Art Inc.](https://www.permitgraph.org/contractor/ad-art-inc-826051) | to erect a projecting and electrical sign. | $5,000 |
| [201208036455](https://www.permitgraph.org/p/201208036455) | Aug 3, 2012 | Completed: final sign-off Nov 2012 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Kaiser Foundation Health Plan Inc](https://www.permitgraph.org/contractor/kaiser-foundation-health-plan-inc-370871) | installing one new smoke detector in tr room. | $5,000 |
| [201206132499](https://www.permitgraph.org/p/201206132499) | Jun 13, 2012 | Completed: final sign-off Nov 2012 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | 1st floor ti for new telephone roomincludes selective demolition, (n) partitions, installation of (n) electric receptacles, (n) it equipment storage racks, 1 (n) 1 ton fan coil unit & 1 (n) smoke det… | $80,000 |
| [201206132495](https://www.permitgraph.org/p/201206132495) | Jun 13, 2012 | Completed: final sign-off Dec 2013 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Kaiser Foundation Health Plan Inc](https://www.permitgraph.org/contractor/kaiser-foundation-health-plan-inc-370871) | bldg maintenance includes: coating of (e) bldg ext, patch & repair of selectively demolished portions of ext. bldg shell, patch & repair (e) exterior surfaces, replace (e) exterior lighting, remvoal… | $180,000 |
| [201112201019](https://www.permitgraph.org/p/201112201019) | Dec 20, 2011 | Completed: final sign-off Mar 2012 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Kaiser Foundation Health Plan Inc](https://www.permitgraph.org/contractor/kaiser-foundation-health-plan-inc-370871) | install 3 new smoke detectors on basement, 2nd and 3rd levels. | $2,500 |
| [201111229449](https://www.permitgraph.org/p/201111229449) | Nov 22, 2011 | Completed: final sign-off May 2016 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Kaiser Foundation Health Plan Inc](https://www.permitgraph.org/contractor/kaiser-foundation-health-plan-inc-370871) | install 5 new smoke detectors. install 3 new interface modules. | $5,000 |
| [201105035208](https://www.permitgraph.org/p/201105035208) | May 3, 2011 | Completed: final sign-off Apr 2012 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Kaiser Foundation Health Plan Inc](https://www.permitgraph.org/contractor/kaiser-foundation-health-plan-inc-370871) | upgrade existing elec and mech cooling system for main building telecommunication room, in building basement. installation new telecomm equip in both btr and auxillary telecommunication rooms on uppe… | $250,000 |
| [201006184788](https://www.permitgraph.org/p/201006184788) | Jun 18, 2010 | Completed: final sign-off Aug 2010 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Kaiser Foundation Health Plan Inc](https://www.permitgraph.org/contractor/kaiser-foundation-health-plan-inc-370871) | 1st flr: install 2 new smoke detectors, relocate 2 existing smoke detectors, 1 new chrome/strobes, install 1 new strobe | $5,000 |
| [201002247042](https://www.permitgraph.org/p/201002247042) | Feb 24, 2010 | Completed: final sign-off Aug 2010 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Kaiser Foundation Health Plan Inc](https://www.permitgraph.org/contractor/kaiser-foundation-health-plan-inc-370871) | kaiser. remodel various cardiology dept. areas including the reception and waiting areas and adjacent offices and work on first floor | $50,000 |
| [M182786](https://www.permitgraph.org/p/M182786) | Oct 26, 2009 | Never finaled: issued Oct 2009, no final | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | street space only |  |
| [200901230708](https://www.permitgraph.org/p/200901230708) | Jan 23, 2009 | Completed: final sign-off Jul 2009 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | remodel of (e) waiting area, reception, work area & office. construction of new accessible transaction counter | $230,000 |
| [200812188728](https://www.permitgraph.org/p/200812188728) | Dec 18, 2008 | Completed: final sign-off Jan 2010 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | replace 133 existing windows - single panel aluminum. 133 new double panel - low efficiency windows-aluminum | $30,000 |
| [200805091689](https://www.permitgraph.org/p/200805091689) | May 9, 2008 | Completed: final sign-off Oct 2008 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | water intrusion remodeling-west exit corridor roof canopy, concrete site work on exit corridor, pavement to exterior wall joint sealant, pavement joint sealant, masonry wainscoting sealant | $50,000 |
| [200804179931](https://www.permitgraph.org/p/200804179931) | Apr 17, 2008 | Completed: final sign-off Oct 2008 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | 2nd floor-remodel various department areas (office), including reception and some adjacent areas which involves non-load bearing walls and rebuild partition wall for new offices/flooring | $300,000 |
| [200801071935](https://www.permitgraph.org/p/200801071935) | Jan 7, 2008 | Completed: final sign-off Apr 2008 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | barrier removal - remodel toilet room on 2nd floor to make it ada compliant on room 225. | $3,000 |
| [200708078940](https://www.permitgraph.org/p/200708078940) | Aug 7, 2007 | Completed: final sign-off Nov 2007 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | revision to approved appl. 2007 0212 3942: modify structural floor framing. install new glulam beams at ground floor, new posts at ground and basement floor, and new concrete footings, all where and… | $50,000 |
| [200702123942](https://www.permitgraph.org/p/200702123942) | Feb 12, 2007 | Completed: final sign-off Nov 2007 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | remodel (e) office area to a (n) echo suite area, no structural work. replacement of ceiling & lighting. | $40,000 |
| [200609122085](https://www.permitgraph.org/p/200609122085) | Sep 12, 2006 | Never finaled: issued Oct 2006, no final | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | erect: wall, non illuminated new sign | $4,000 |
| [200609122078](https://www.permitgraph.org/p/200609122078) | Sep 12, 2006 | Never finaled: issued Oct 2006, no final | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | erect sign - wall, single faced, non-electric, non illuminated new sign. | $8,931 |
| [200512069552](https://www.permitgraph.org/p/200512069552) | Dec 6, 2005 | Completed: final sign-off Jan 2006 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | interior tenant improvement remove one non load bearing wall build 2 offices and 1 work area. | $40,000 |
| [200506225687](https://www.permitgraph.org/p/200506225687) | Jun 22, 2005 | Completed: final sign-off Apr 2006 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Kaiser Foundation Health Plan Inc](https://www.permitgraph.org/contractor/kaiser-foundation-health-plan-inc-370871) | new electrical outlets, mechanical cooling equipment @ (e) telecommunication areas, mep permit only. | $80,000 |
| [200501112967](https://www.permitgraph.org/p/200501112967) | Jan 11, 2005 | Completed: final sign-off Apr 2005 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Mc Carthy Building Companies Inc](https://www.permitgraph.org/contractor/mc-carthy-building-companies-inc-411173) | renew permit 200406015179-200303119329-200309164962 for final inspection only |  |
| [200406015179](https://www.permitgraph.org/p/200406015179) | Jun 1, 2004 | Expired or cancelled: expired Apr 2005 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Mc Carthy Building Companies Inc](https://www.permitgraph.org/contractor/mc-carthy-building-companies-inc-411173) | scope limited to installation of magnetic door,hold open & smoke detector @door,removal of drinking | $12,500 |
| [200309164962](https://www.permitgraph.org/p/200309164962) | Sep 16, 2003 | Completed: final sign-off Apr 2005 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Mc Carthy Building Companies Inc](https://www.permitgraph.org/contractor/mc-carthy-building-companies-inc-411173) | add fire alarm devices for ada remediation - work included under previous approved pa#200303119329 |  |
| [200303119329](https://www.permitgraph.org/p/200303119329) | Mar 11, 2003 | Never finaled: issued May 2003, no final | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Mc Carthy Building Companies Inc](https://www.permitgraph.org/contractor/mc-carthy-building-companies-inc-411173) | ada compliance, remediation work | $69,000 |
| [200206078519](https://www.permitgraph.org/p/200206078519) | Jun 7, 2002 | Completed: final sign-off Aug 2002 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | renew app 9811692 for final inspeciton | $10,000 |
| [200205317961](https://www.permitgraph.org/p/200205317961) | May 31, 2002 | Completed: final sign-off Aug 2002 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) |  | renew appl#20000203991 & 9907738 for remaining work | $20,000 |
| [20000203991](https://www.permitgraph.org/p/20000203991) | Feb 3, 2000 | Expired or cancelled: expired Jun 2001 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Kaiser Foundtion Hosp](https://www.permitgraph.org/contractor/kaiser-foundtion-hosp-187350) | renewal of application 9907738 |  |
| [20000203993](https://www.permitgraph.org/p/20000203993) | Feb 3, 2000 | Expired or cancelled: expired Jun 2000 | [2350 Geary Bl](https://www.permitgraph.org/a/1080/034) | [Kaiser Foundtion Hosp](https://www.permitgraph.org/contractor/kaiser-foundtion-hosp-187350) | renewal of application 9611282 |  |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Kaiser Foundation Health Plan Inc](https://www.permitgraph.org/contractor/kaiser-foundation-health-plan-inc-370871) (8), [Mc Carthy Building Companies Inc](https://www.permitgraph.org/contractor/mc-carthy-building-companies-inc-411173) (4), [Kaiser Foundtion Hosp](https://www.permitgraph.org/contractor/kaiser-foundtion-hosp-187350) (2), [Ad Art Inc.](https://www.permitgraph.org/contractor/ad-art-inc-826051), [Turner Construction Co](https://www.permitgraph.org/contractor/turner-construction-co-210639), [W. Bradley Electric](https://www.permitgraph.org/contractor/w-bradley-electric-1114449)
- Architects: [Carl A Scholz](https://www.permitgraph.org/professional/carl-a-scholz-C4822), [Darren Matano](https://www.permitgraph.org/professional/darren-matano-C28417), [Jason Brabo](https://www.permitgraph.org/professional/jason-brabo-C29632), [Mehrnoush Arsanjani](https://www.permitgraph.org/professional/mehrnoush-arsanjani-C21224), [Michelle Eaton](https://www.permitgraph.org/professional/michelle-eaton-C17020)
- Engineers: [Ali Mortzavi](https://www.permitgraph.org/professional/ali-mortzavi-E20334)
- Authorized agents: [Erik Ellingsen](https://www.permitgraph.org/professional/erik-ellingsen-C81269)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/a/1080/034.