# 1390 Market St

Block 0813, lot 009. Page: https://www.permitgraph.org/a/0813/009

- City's use: Commercial Office
- Built: 1967
- Stories: 12
- Building: 215,510 sq ft
- Lot: 26,972 sq ft
- Zoning: C3G
- Construction type: NA

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

13 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [201808066505](https://www.permitgraph.org/p/201808066505) | Aug 6, 2018 | Completed: final sign-off Jan 2019 | [1390 Market St](https://www.permitgraph.org/a/0813/009) | [Red Hawk Fire & Security Ca Llc](https://www.permitgraph.org/contractor/red-hawk-fire-security-ca-llc-713099) | suite 100: relocate, add and demo sprinklers for new bank t.i. ref pa201804126233. maher n/a. | $50,000 |
| [201405095313](https://www.permitgraph.org/p/201405095313) | May 9, 2014 | Completed: final sign-off Jul 2014 | [1390 Market St](https://www.permitgraph.org/a/0813/009) | [Skyline Construction](https://www.permitgraph.org/contractor/skyline-construction-727637) | 4th floor: suite 405 and 406: minor demolition of non-load bearing partitions. installation of new clg. height partitions to include new bldg and hvac as required. mep scope is design-build under sep… | $49,841 |
| [201404223804](https://www.permitgraph.org/p/201404223804) | Apr 22, 2014 | Completed: final sign-off Aug 2014 | [1390 Market St](https://www.permitgraph.org/a/0813/009) | [Skyline Construction](https://www.permitgraph.org/contractor/skyline-construction-727637) | 9th floor - demolition & replacement of (e) ceiling grid, tile & light fixtures @ common corridor & elevator lobby. mep, fire, life safety is design build & under separate permit. compliance with ord… | $119,727 |
| [201403130681](https://www.permitgraph.org/p/201403130681) | Mar 13, 2014 | Completed: final sign-off Apr 2014 | [1390 Market St](https://www.permitgraph.org/a/0813/009) | [Principal Builders Inc.](https://www.permitgraph.org/contractor/principal-builders-inc-829808) | revision to previous app# 201402047723 to delete elevator lobby card reader off existing approved plans. n/a for the maher ordinance #155-13 and n/a for the interim controls #428-13 |  |
| [201403060042](https://www.permitgraph.org/p/201403060042) | Mar 6, 2014 | Never finaled: issued Mar 2014, no final | [1390 Market St](https://www.permitgraph.org/a/0813/009) | [Principal Builders Inc.](https://www.permitgraph.org/contractor/principal-builders-inc-829808) | 10th floor:title -24 mechanical and electrical to upgrade equipment on 10th floor plan ref app#201402047723 for t.i. referance. n/a for the maher ordinance #155-13 and n/a for the interim controls #4… | $40,000 |
| [201402047723](https://www.permitgraph.org/p/201402047723) | Feb 4, 2014 | Completed: final sign-off Apr 2014 | [1390 Market St](https://www.permitgraph.org/a/0813/009) | [Principal Builders Inc.](https://www.permitgraph.org/contractor/principal-builders-inc-829808) | new non load bearing paritions, doors, millwork, new ciling grid and tile as well as new finishes. mechanical, electrical, plumbing, fire, life safety under separate permit. maher ordinance not requi… | $160,343 |
| [201312093646](https://www.permitgraph.org/p/201312093646) | Dec 9, 2013 | Never finaled: issued Dec 2013, no final | [1390 Market St](https://www.permitgraph.org/a/0813/009) | [Red Hawk Fire & Security Ca Llc](https://www.permitgraph.org/contractor/red-hawk-fire-security-ca-llc-713099) | ti adding 1 smoke detector, 5 speaker/strobes, 8 speakers, ref pa#2013.1113.1739 | $7,000 |
| [201311141921](https://www.permitgraph.org/p/201311141921) | Nov 14, 2013 | Never finaled: issued Jan 2015, no final | [1390 Market St](https://www.permitgraph.org/a/0813/009) | [Principal Builders Inc.](https://www.permitgraph.org/contractor/principal-builders-inc-829808) | 8th floor suite 810 & 815 - install ductiles split air conditioner system, grilles & ductwork on t.i. refer ot pa #2013.11.13.1739 for ti work | $80,000 |
| [201311131739](https://www.permitgraph.org/p/201311131739) | Nov 13, 2013 | Completed: final sign-off Feb 2014 | [1390 Market St](https://www.permitgraph.org/a/0813/009) | [Principal Builders Inc.](https://www.permitgraph.org/contractor/principal-builders-inc-829808) | 8th floor ste 810 - work to include demo of non-load bearing partitions & doors, installation of (n) ceiling height partitions, doors, & finishes, relcoation of (e) light fixtures, mech & electrical.… | $151,511 |
| [201310240104](https://www.permitgraph.org/p/201310240104) | Oct 24, 2013 | Completed: final sign-off Mar 2014 | [1390 Market St](https://www.permitgraph.org/a/0813/009) | [Ayoob & Peery Plumbing Co Inc](https://www.permitgraph.org/contractor/ayoob-peery-plumbing-co-inc-392967) | 3rd floor:add fire sprinkler heads per t.i. add 46 heads. ref app#201308265240. | $23,644 |
| [201309035839](https://www.permitgraph.org/p/201309035839) | Sep 3, 2013 | Completed: final sign-off Apr 2014 | [1390 Market St](https://www.permitgraph.org/a/0813/009) | [Principal Builders Inc.](https://www.permitgraph.org/contractor/principal-builders-inc-829808) | mechanical and electrical work on 3rd floor ti. to relocate and add fixtures and equiptment. ref #201308265240. fa & ls to be submited on separarate permits> jjc | $50,000 |
| [201308265240](https://www.permitgraph.org/p/201308265240) | Aug 26, 2013 | Completed: final sign-off Apr 2014 | [1390 Market St](https://www.permitgraph.org/a/0813/009) | [Principal Builders Inc.](https://www.permitgraph.org/contractor/principal-builders-inc-829808) | suite 310:demolition of non-load bearing partitions & doors,new cieling heights partitions, millwork & finishes & reuse of extg doorsat area of remodel only. relocation of extg lighting, mechanical,… | $161,945 |
| [201308265238](https://www.permitgraph.org/p/201308265238) | Aug 26, 2013 | Never finaled: issued Sep 2013, no final | [1390 Market St](https://www.permitgraph.org/a/0813/009) | [Principal Builders Inc.](https://www.permitgraph.org/contractor/principal-builders-inc-829808) | suite 908:demolition of non-load bearing partitions and doors, flooring and millwork. relocation of extg lighting, mechanical, and electrical under seperate permit. | $35,450 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Principal Builders Inc.](https://www.permitgraph.org/contractor/principal-builders-inc-829808) (8), [Red Hawk Fire & Security Ca Llc](https://www.permitgraph.org/contractor/red-hawk-fire-security-ca-llc-713099) (2), [Skyline Construction](https://www.permitgraph.org/contractor/skyline-construction-727637) (2), [Ayoob & Peery Plumbing Co Inc](https://www.permitgraph.org/contractor/ayoob-peery-plumbing-co-inc-392967)
- Architects: [Joel Karr](https://www.permitgraph.org/professional/joel-karr-C29051) (2)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.