# 506 Grove St

Block 0794, lot 004. Page: https://www.permitgraph.org/a/0794/004

- City's use: Multi-Family Residential
- Built: 1927
- Stories: 3
- Units: 19
- Rooms: 19 bedrooms, 19 bathrooms
- Building: 9,105 sq ft
- Lot: 3,296 sq ft
- Zoning: RM1
- Construction type: D

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

11 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [202405242894](https://www.permitgraph.org/p/202405242894) | May 24, 2024 | In progress: issued May 2024 | [506 Grove St](https://www.permitgraph.org/a/0794/004) | [International Fire Inc](https://www.permitgraph.org/contractor/international-fire-inc-965370) | upgrade (e) fire alarm system in partly sprinkled building to comply with 2022 cbc/cfc, nfpa 72 and sffc sec 1103.7.6.1. replace (e) facu and add radio to monitor system . smokes in common areas and… | $25,000 |
| [202108247050](https://www.permitgraph.org/p/202108247050) | Aug 24, 2021 | Completed: final sign-off Oct 2021 | [506 Grove St](https://www.permitgraph.org/a/0794/004) | [Level 8 Construction Inc](https://www.permitgraph.org/contractor/level-8-construction-inc-851171) | unit 205: repair plumbing. remodel 1 bathroom. no structural work. comply to complain # 202179275. | $10,000 |
| [202105039675](https://www.permitgraph.org/p/202105039675) | May 3, 2021 | Expired or cancelled: cancelled Feb 2026 | [506 Grove St](https://www.permitgraph.org/a/0794/004) |  | upgrade kitchen & bathrom: reinstall sink, toilet, upgrade to kitchen and bathroom in unit 206. replace existing kitchen cabinets, counter top, replace existing bathroom sink, all existing plumbing w… | $2,000 |
| [202103307510](https://www.permitgraph.org/p/202103307510) | Mar 30, 2021 | Completed: final sign-off Jul 2021 | [506 Grove St](https://www.permitgraph.org/a/0794/004) |  | apt 206: upgrade kitchen & bathroom electric. reinstall sinks, tolet, upgrade to kitchen & bathroom. replace (e) kitchen cabinets , counter top & floor tile inkind replace (e) tile in bathroom shower… | $17,000 |
| [202003167166](https://www.permitgraph.org/p/202003167166) | Mar 16, 2020 | Completed: final sign-off May 2020 | [506 Grove St](https://www.permitgraph.org/a/0794/004) |  | unit #204:to comply with nov 202023501. upgrade kitchen and bathroom elect. replace kitchen cabinets, countertop and floor tiles in kind. | $17,000 |
| [201805098631](https://www.permitgraph.org/p/201805098631) | May 9, 2018 | Completed: final sign-off Oct 2018 | [506 Grove St](https://www.permitgraph.org/a/0794/004) | [Michael E Miranda General Contractor](https://www.permitgraph.org/contractor/michael-e-miranda-general-contractor-919055) | apt 104: upgrade kichen & bathrom elect. reinstall sinks, toilet upgrades to kitchen & bathroom in unit. replace (e) kitchen cabinets, countertop & tile in-kind.replace (e) tile in bathrom shower sur… | $7,000 |
| [201510301360](https://www.permitgraph.org/p/201510301360) | Oct 30, 2015 | Completed: final sign-off Mar 2017 | [506 Grove St](https://www.permitgraph.org/a/0794/004) | [Michael E Miranda General Contractor](https://www.permitgraph.org/contractor/michael-e-miranda-general-contractor-919055) | soft story compliance: method 2012 iebc appendix a-4. mandatory seismic retrofit per sfbc chapter 34 b bldg reinforcment. rigid frames add anchor sill bolting to foundation, add plywood to walls and… | $60,000 |
| [201208298487](https://www.permitgraph.org/p/201208298487) | Aug 29, 2012 | Completed: final sign-off May 2013 | [506 Grove St](https://www.permitgraph.org/a/0794/004) | [Econoquality Inc](https://www.permitgraph.org/contractor/econoquality-inc-937548) | ground floor only-remove (e) non bearing walls, partition walls, remove (e) doors, new tile floor, new washer/dryer units. new hot/cold water supply. new electrical sub panel, 4 new electrical 20 amp… | $8,000 |
| [M169125](https://www.permitgraph.org/p/M169125) | Jun 19, 2009 | Never finaled: issued Jun 2009, no final | [506 Grove St](https://www.permitgraph.org/a/0794/004) |  | street space permit only. |  |
| [200708159872](https://www.permitgraph.org/p/200708159872) | Aug 15, 2007 | Completed: final sign-off Sep 2007 | [506 Grove St](https://www.permitgraph.org/a/0794/004) | [Star 1 M S Inc](https://www.permitgraph.org/contractor/star-1-m-s-inc-811329) | install foundation bolts to plate at entire perimerter of building as per plan. | $4,000 |
| [200305225302](https://www.permitgraph.org/p/200305225302) | May 22, 2003 | Completed: final sign-off Aug 2003 | [506 Grove St](https://www.permitgraph.org/a/0794/004) |  | comply w/nov 2002313137;(remove illegal unit);to correct cfc 9200776 record from 18 to 19 units | $10,000 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Michael E Miranda General Contractor](https://www.permitgraph.org/contractor/michael-e-miranda-general-contractor-919055) (2), [Econoquality Inc](https://www.permitgraph.org/contractor/econoquality-inc-937548), [International Fire Inc](https://www.permitgraph.org/contractor/international-fire-inc-965370), [Level 8 Construction Inc](https://www.permitgraph.org/contractor/level-8-construction-inc-851171), [Star 1 M S Inc](https://www.permitgraph.org/contractor/star-1-m-s-inc-811329)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/a/0794/004.