# 1251 Turk St

Block 0757, lot 028. Page: https://www.permitgraph.org/a/0757/028

The city's assessor roll has no record for this parcel.

## Permits filed here

19 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [M816727](https://www.permitgraph.org/p/M816727) | Aug 7, 2017 | Never finaled: issued Aug 2017, no final | [1251 Turk St](https://www.permitgraph.org/a/0757/028) |  | street spae permit |  |
| [201704214599](https://www.permitgraph.org/p/201704214599) | Apr 21, 2017 | Completed: final sign-off Nov 2018 | [1251 Turk St](https://www.permitgraph.org/a/0757/028) | [International Fire Inc](https://www.permitgraph.org/contractor/international-fire-inc-965370) | upgrade existing fire alarm system per sffc sec 1103.7.6.1 install low frequency sounders in every unit on all floors. new power supply panels and control modules on 2nd-11th fl to be supervised noti… | $75,000 |
| [201702068724](https://www.permitgraph.org/p/201702068724) | Feb 6, 2017 | Never finaled: issued Feb 2017, no final | [1251 Turk St](https://www.permitgraph.org/a/0757/028) | [Rcm Fire Protection Inc.](https://www.permitgraph.org/contractor/rcm-fire-protection-inc-793205) | commencement of work not started under previously approved permit application #201601298339. | $10,000 |
| [201702018386](https://www.permitgraph.org/p/201702018386) | Feb 1, 2017 | Completed: final sign-off Nov 2018 | [1251 Turk St](https://www.permitgraph.org/a/0757/028) | [Access Systems & Solutions Inc](https://www.permitgraph.org/contractor/access-systems-solutions-inc-922381) | install roof mounted and wall mounted bases on the main roof for exterior building maintenance ref 201501162685 | $80,000 |
| [201701207565](https://www.permitgraph.org/p/201701207565) | Jan 20, 2017 | Completed: final sign-off Nov 2018 | [1251 Turk St](https://www.permitgraph.org/a/0757/028) | [International Fire Inc](https://www.permitgraph.org/contractor/international-fire-inc-965370) | as built to app#201608266094. install monitor module to tie-in, 2 duct detectors and 2 fsd to extg control panel.install 4 strobes and 1 horn/strobe on the ground floor. replace strobes with horn/str… | $3,000 |
| [201612165199](https://www.permitgraph.org/p/201612165199) | Dec 16, 2016 | Completed: final sign-off Nov 2018 | [1251 Turk St](https://www.permitgraph.org/a/0757/028) | [Cahill Const Service Inc](https://www.permitgraph.org/contractor/cahill-const-service-inc-495085) | revision to incorporate m.o.d. approvals to pa#201511162685. |  |
| [201608266094](https://www.permitgraph.org/p/201608266094) | Aug 26, 2016 | Completed: final sign-off Nov 2018 | [1251 Turk St](https://www.permitgraph.org/a/0757/028) | [International Fire Inc](https://www.permitgraph.org/contractor/international-fire-inc-965370) | install new low freq notification appliances & smk det. inside ada rms. install strobes in the bathrooms inside ada rms. install new power supply panels & modules to supervised new notification circu… | $55,000 |
| [201604084296](https://www.permitgraph.org/p/201604084296) | Apr 8, 2016 | Completed: final sign-off Jun 2016 | [1251 Turk St](https://www.permitgraph.org/a/0757/028) | [International Fire Inc](https://www.permitgraph.org/contractor/international-fire-inc-965370) | fire alarm as built for pa# 201501165984 |  |
| [201601298339](https://www.permitgraph.org/p/201601298339) | Jan 29, 2016 | Completed: final sign-off Nov 2018 | [1251 Turk St](https://www.permitgraph.org/a/0757/028) | [Rcm Fire Protection Inc.](https://www.permitgraph.org/contractor/rcm-fire-protection-inc-793205) | change out extg sprinkler heads for t.i. reference ti 2015.1116.2685 not issued yet. | $10,000 |
| [201511162685](https://www.permitgraph.org/p/201511162685) | Nov 16, 2015 | Completed: final sign-off Nov 2018 | [1251 Turk St](https://www.permitgraph.org/a/0757/028) | [Cahill Contractors Inc](https://www.permitgraph.org/contractor/cahill-contractors-inc-300647) | mohcd rad.remove/replace all(e)extr windows.provide(n)extr elastomerk paint to extr & make extr cladding repairs in-kind. provide(n)grnd fl finishes & grnd fl reconfig of(e)admin spaces. replace kitc… | $20,000,000 |
| [201501165984](https://www.permitgraph.org/p/201501165984) | Jan 16, 2015 | Completed: final sign-off Jun 2016 | [1251 Turk St](https://www.permitgraph.org/a/0757/028) | [International Fire Inc](https://www.permitgraph.org/contractor/international-fire-inc-965370) | like for like voluntary fire alarm system replacment. replace existing fire alarm constrol unit with new at the same location. replace existing initiating notification devices with new at the same lo… | $38,000 |
| [201403180984](https://www.permitgraph.org/p/201403180984) | Mar 18, 2014 | Never finaled: issued Mar 2014, no final | [1251 Turk St](https://www.permitgraph.org/a/0757/028) | [Cosco Fire Protection Inc.](https://www.permitgraph.org/contractor/cosco-fire-protection-inc-577621) | relocate 6" fire service from turk st. to webster st & install new 6" ddc. comply with cfc 2013 - fire safety chapter 33. | $55,000 |
| [201401095907](https://www.permitgraph.org/p/201401095907) | Jan 9, 2014 | Completed: final sign-off Nov 2018 | [1251 Turk St](https://www.permitgraph.org/a/0757/028) | [Cahill Contractors Inc](https://www.permitgraph.org/contractor/cahill-contractors-inc-300647) | construct temporary surface parking & temporary drop off total of 29 spaces. repairs to existing building trash room. per planning request. related to app#201207104447. | $500,000 |
| [201202295106](https://www.permitgraph.org/p/201202295106) | Feb 29, 2012 | Completed: final sign-off Mar 2012 | [1111 Buchanan St](https://www.permitgraph.org/a/0757/028) | [San Francisco Fire Protection](https://www.permitgraph.org/contractor/san-francisco-fire-protection-806216) | reference app#201103182353 to this appn. is change to ref appn. eliminate monitoring by extg facp at 1251 turk. remove three relay modules from plans and change job address to 1111 buchanan street. p… | $600 |
| [201202144148](https://www.permitgraph.org/p/201202144148) | Feb 14, 2012 | Expired or cancelled: withdrawn Nov 2018 | [1251 Turk St](https://www.permitgraph.org/a/0757/028) |  | remove & replace existing domestic hot water heaters & cogeneration unit installed in same locations and weigh less. | $350,000 |
| [201108011434](https://www.permitgraph.org/p/201108011434) | Aug 1, 2011 | Never finaled: issued Aug 2011, no final | [1111 Buchanan St](https://www.permitgraph.org/a/0757/028) | [D & S Leong Associates](https://www.permitgraph.org/contractor/d-s-leong-associates-618294) | install 9 heads in new hallway on ground floor only. | $5,000 |
| [201103182353](https://www.permitgraph.org/p/201103182353) | Mar 18, 2011 | Completed: final sign-off Mar 2012 | [1251 Turk St](https://www.permitgraph.org/a/0757/028) | [San Francisco Fire Protection](https://www.permitgraph.org/contractor/san-francisco-fire-protection-806216) | install 1 fire panel, 1 annunuator, 17 notification devices, 7 manual pulls & 27 smoke detectors | $18,000 |
| [201009100604](https://www.permitgraph.org/p/201009100604) | Sep 10, 2010 | Never finaled: issued Dec 2010, no final | [1251 Turk St](https://www.permitgraph.org/a/0757/028) | [Transworld Construction](https://www.permitgraph.org/contractor/transworld-construction-371269) | enclosed walkay addition, elevator upgrades, exterior (n) ramp and walkways, lighting and landscaping. note: see pa #2010-0629-5562 for related work on the senior center (1111 buchanan st.) that shar… | $212,500 |
| [201006295562](https://www.permitgraph.org/p/201006295562) | Jun 29, 2010 | Never finaled: issued Dec 2010, no final | [1111 Buchanan St](https://www.permitgraph.org/a/0757/028) | [Transworld Construction](https://www.permitgraph.org/contractor/transworld-construction-371269) | exterior paint, replace all windows/doors. (n) site access gate, exterior ramp/walkways, landscape. interior ada upgrades to (e) bathrooms, (n) accessible toilet rooms, interior renovation. see pa #2… | $1,941,237 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [International Fire Inc](https://www.permitgraph.org/contractor/international-fire-inc-965370) (5), [Cahill Contractors Inc](https://www.permitgraph.org/contractor/cahill-contractors-inc-300647) (2), [Rcm Fire Protection Inc.](https://www.permitgraph.org/contractor/rcm-fire-protection-inc-793205) (2), [San Francisco Fire Protection](https://www.permitgraph.org/contractor/san-francisco-fire-protection-806216) (2), [Transworld Construction](https://www.permitgraph.org/contractor/transworld-construction-371269) (2), [Access Systems & Solutions Inc](https://www.permitgraph.org/contractor/access-systems-solutions-inc-922381), [Cahill Const Service Inc](https://www.permitgraph.org/contractor/cahill-const-service-inc-495085), [Cosco Fire Protection Inc.](https://www.permitgraph.org/contractor/cosco-fire-protection-inc-577621), [D & S Leong Associates](https://www.permitgraph.org/contractor/d-s-leong-associates-618294)
- Architects: [Toby Stella Levy](https://www.permitgraph.org/professional/toby-stella-levy-C10527) (2), [Michael Willis](https://www.permitgraph.org/professional/michael-willis-C15140), [Pamela Anee Collier](https://www.permitgraph.org/professional/pamela-anee-collier-C14940)
- Engineers: [Ali G Mahalatinia](https://www.permitgraph.org/professional/ali-g-mahalatinia-C38446), [Donald Wulschleger](https://www.permitgraph.org/professional/donald-wulschleger-E13522), [R.E. Spitzka](https://www.permitgraph.org/professional/r-e-spitzka-M13131)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/a/0757/028.