# 55 Stockton St

Block 0327, lot 002. Page: https://www.permitgraph.org/a/0327/002

- City's use: Commercial Retail
- Built: 1989
- Stories: 8
- Units: 9
- Building: 100,715 sq ft
- Lot: 2,269 sq ft
- Zoning: C3R
- Construction type: A

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

59 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [202604038881](https://www.permitgraph.org/p/202604038881) | Apr 3, 2026 | Completed: final sign-off Oct 2026 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Martin Sign Co Inc.](https://www.permitgraph.org/contractor/martin-sign-co-inc-980058) | 1 aluminum illuminated/electrical, 2 face sign. sign name as "chalk" | $16,437 |
| [202502110097](https://www.permitgraph.org/p/202502110097) | Feb 11, 2025 | Completed: final sign-off Apr 2025 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Everon Llc](https://www.permitgraph.org/contractor/everon-llc-1065604) | tenant improvement on 7th fl. addition of 12 ceiling mounted speaker strobes and 2 ceiling mounted speakers is added to the (e) fire alarm system | $17,858 |
| [202501279105](https://www.permitgraph.org/p/202501279105) | Jan 27, 2025 | Completed: final sign-off Mar 2025 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) |  | 7/fl-ti 202411265728- fire sprinkler to relocated 26 and add 11 sprinklers | $12,000 |
| [202411265728](https://www.permitgraph.org/p/202411265728) | Nov 26, 2024 | Completed: final sign-off May 2025 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Paradigm General Contractors](https://www.permitgraph.org/contractor/paradigm-general-contractors-608135) | suite 700/7th fl ti demo of non structural partitions and building non structural partitions. new millwork, new finishes.e full floor suite will be demised into 2 suites. mep included. deferred submi… | $637,537 |
| [202309186757](https://www.permitgraph.org/p/202309186757) | Sep 18, 2023 | Completed: final sign-off Sep 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Paradigm General Contractors](https://www.permitgraph.org/contractor/paradigm-general-contractors-608135) | 7/f revision to pa# 202303093308, to relocate new ada toilet to opposite side due to existing bldg vertical pipes. no change of use. |  |
| [202306089574](https://www.permitgraph.org/p/202306089574) | Jun 8, 2023 | Completed: final sign-off Jul 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Urban Graphics Inc](https://www.permitgraph.org/contractor/urban-graphics-inc-1078591) | 7/f: install 4 evacuation maps. | $2,000 |
| [202306079430](https://www.permitgraph.org/p/202306079430) | Jun 7, 2023 | Completed: final sign-off Jun 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Everon Llc](https://www.permitgraph.org/contractor/everon-llc-1065604) | 7/f: t.i.: add 7 ceiling speaker/strobes, add 1 ceiling strobe only, add 2 optical smoke detectors. ref pa 202303093308 | $11,500 |
| [202305188113](https://www.permitgraph.org/p/202305188113) | May 18, 2023 | Completed: final sign-off Jun 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [C B F Inc](https://www.permitgraph.org/contractor/c-b-f-inc-335873) | lobby: title 24 compliance for new power & signal devices. ref t.i. pa 202205053663. | $199,000 |
| [202304145733](https://www.permitgraph.org/p/202304145733) | Apr 14, 2023 | Completed: final sign-off Jun 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Paradigm General Contractors](https://www.permitgraph.org/contractor/paradigm-general-contractors-608135) | deferred mechanical for 202205053663 |  |
| [202304065154](https://www.permitgraph.org/p/202304065154) | Apr 6, 2023 | Completed: final sign-off May 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) |  | 7/f: t.i., relocate (8) (e) sprinkers, add (11) new sprinklers. no other work. ref bpa#202303093308 | $2,500 |
| [202303304718](https://www.permitgraph.org/p/202303304718) | Mar 30, 2023 | Completed: final sign-off Apr 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Urban Graphics Inc](https://www.permitgraph.org/contractor/urban-graphics-inc-1078591) | lobby evacuation plans x2 | $1,000 |
| [202303093308](https://www.permitgraph.org/p/202303093308) | Mar 9, 2023 | Completed: final sign-off Sep 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Paradigm General Contractors](https://www.permitgraph.org/contractor/paradigm-general-contractors-608135) | 7/f: internal removations, architectural and meps (1708 sqft) no change of use. fully sprinklered bldg. (suite 700/balconies not occupied, under separate permit for future tenant) | $429,250 |
| [202302021246](https://www.permitgraph.org/p/202302021246) | Feb 2, 2023 | Completed: final sign-off Mar 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Urban Graphics Inc](https://www.permitgraph.org/contractor/urban-graphics-inc-1078591) | 8th fl evacuation plans x4 | $2,000 |
| [202301069763](https://www.permitgraph.org/p/202301069763) | Jan 6, 2023 | Completed: final sign-off Feb 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Everon Llc](https://www.permitgraph.org/contractor/everon-llc-1065604) | 1st floor: fire alarm t.i. to replace 3 extg horn/strobe with new & add 1 strobe only. ref pa# 202205053663 | $2,600 |
| [202212228990](https://www.permitgraph.org/p/202212228990) | Dec 22, 2022 | Completed: final sign-off Feb 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Everon Llc](https://www.permitgraph.org/contractor/everon-llc-1065604) | fire alarm ti suite 8000 add 21 speaker strobes, 1 strobe, 4 speakers, 5 weatherproof speakers ref 202210063919 | $17,000 |
| [202211166606](https://www.permitgraph.org/p/202211166606) | Nov 16, 2022 | Completed: final sign-off Jan 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) |  | 8th floor:fire sprinkler permit. relocate 23, add 5 and delete 9 pendent sprinklers. relocate 15, add 37 and delete 9 sidewall sprinklers on the floor. t.i. 202210063919 | $27,000 |
| [202211035783](https://www.permitgraph.org/p/202211035783) | Nov 3, 2022 | Expired or cancelled: cancelled Mar 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) |  | ti to 5th fl. relocate 12 sprinklers. add 6 sprinklers. no other work to system. ref pa 202209162596. | $1,000 |
| [202210315551](https://www.permitgraph.org/p/202210315551) | Oct 31, 2022 | Completed: final sign-off Jul 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Paradigm General Contractors](https://www.permitgraph.org/contractor/paradigm-general-contractors-608135) | floors 7/8: project is proving new stainless steel. "horizontal" cables to the existing non compliant metal guradrails to tighten up picket spacing. | $175,000 |
| [202210063919](https://www.permitgraph.org/p/202210063919) | Oct 6, 2022 | Completed: final sign-off Apr 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Paradigm General Contractors](https://www.permitgraph.org/contractor/paradigm-general-contractors-608135) | 8th fl interior renovation. approx construction area 6,755 sqft. scope includes architectural and meps. | $1,925,021 |
| [202209192689](https://www.permitgraph.org/p/202209192689) | Sep 19, 2022 | Never finaled: issued Sep 2022, no final | [55 Stockton St](https://www.permitgraph.org/a/0327/002) |  | lobby: relocate 10 ex pendents, add 1, replace 4 existing with new sprinkler. ref permit 202205053663 | $1,000 |
| [202209162596](https://www.permitgraph.org/p/202209162596) | Sep 16, 2022 | Expired or cancelled: cancelled May 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Paradigm General Contractors](https://www.permitgraph.org/contractor/paradigm-general-contractors-608135) | 5th fl interior renovation. approx scope area 585 sqft. scope includes architectural, electrical, plumbing & mechanical. bldg is fully sprinklered. | $260,000 |
| [202206166481](https://www.permitgraph.org/p/202206166481) | Jun 16, 2022 | Completed: final sign-off Apr 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Paradigm General Contractors](https://www.permitgraph.org/contractor/paradigm-general-contractors-608135) | refurbish lobby entrance (n) exterior tile, refnishing (e) exterior doors and some signage (n) lighting and fixtures. mep deferred no change to exiting/egress. | $5,000 |
| [202205265028](https://www.permitgraph.org/p/202205265028) | May 26, 2022 | Never finaled: issued Jun 2022, no final | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Thomas Swan Sign Co Inc](https://www.permitgraph.org/contractor/thomas-swan-sign-co-inc-269069) | install 1 illuminated wall sign. electric. single faced. "coco republic" (30"x37') | $5,000 |
| [202205265030](https://www.permitgraph.org/p/202205265030) | May 26, 2022 | Completed: final sign-off Nov 2022 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Thomas Swan Sign Co Inc](https://www.permitgraph.org/contractor/thomas-swan-sign-co-inc-269069) | install 2 non-illuminated projecting banners. double faced. "coco republic" (219"x36") | $5,000 |
| [202205053663](https://www.permitgraph.org/p/202205053663) | May 5, 2022 | Completed: final sign-off Jun 2023 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Paradigm General Contractors](https://www.permitgraph.org/contractor/paradigm-general-contractors-608135) | refurbish (e) lobby. work includes (n) floor, (n) wall & (n) ceiling finishes as well as lighting & fixtures. mep deferred. | $65,000 |
| [202108267188](https://www.permitgraph.org/p/202108267188) | Aug 26, 2021 | Completed: final sign-off Mar 2022 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Paradigm General Contractors](https://www.permitgraph.org/contractor/paradigm-general-contractors-608135) | 5/6/7 fl: demo of non-structural partitions, celings, hvac and plumbing.(e) occpy use, egress system, fire rating and constr type unchanged. to comply to ab-017. fire spirnkler heads shall be turned… | $205,000 |
| [202108246992](https://www.permitgraph.org/p/202108246992) | Aug 24, 2021 | Completed: final sign-off Nov 2021 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) |  | flr 5,6,7: sprinkler demolition. remove all existing pendent fire sprinklers (310) and pull all lines to (e) branches. replace with upright sprinklers (215) in (e) outlets. | $2,000 |
| [202011128786](https://www.permitgraph.org/p/202011128786) | Nov 12, 2020 | Expired or cancelled: withdrawn Mar 2021 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Everon Llc](https://www.permitgraph.org/contractor/everon-llc-1065604) | to modify (e) fire alm. on lower l2 & 1st fl. for t.i. nespresso lower l-2 2-new ceiling speaker-strobes. 1 new ceiling strobe. 2-new duct smoke detectors for heat pump control. 2-new remoted test st… | $6,500 |
| [202011038097](https://www.permitgraph.org/p/202011038097) | Nov 3, 2020 | Completed: final sign-off Nov 2020 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Everon Llc](https://www.permitgraph.org/contractor/everon-llc-1065604) | bldg # 2020-0211-4143. lower level 2: (2) new ceiling speaker/strobes, (1) new ceiling strobe 1st floor: (5) new ceiling speaker/strobes, (1) new ceiling strobe, (2) new duct detectors, (2) new contr… | $12,000 |
| [202010015632](https://www.permitgraph.org/p/202010015632) | Oct 1, 2020 | Never finaled: issued Apr 2021, no final | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Big Joe California North Inc](https://www.permitgraph.org/contractor/big-joe-california-north-inc-931417) | installation of stockroom shelving units for existing nespresso store. non high pile storage. no storage over 12'. max height 8'4 | $5,000 |
| [202009184490](https://www.permitgraph.org/p/202009184490) | Sep 18, 2020 | Completed: final sign-off Mar 2021 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Pioneer Fire Inc.](https://www.permitgraph.org/contractor/pioneer-fire-inc-927862) | nespresso - relocate (21) concealed pendents, remove (7) concealed pendents. ref ti 202002114143. | $7,500 |
| [202003025857](https://www.permitgraph.org/p/202003025857) | Mar 2, 2020 | Expired or cancelled: cancelled Jan 2026 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) |  | storefront: recladding storefront frame. replace glass doors in kind. remove worn out threshold. | $20,000 |
| [202002114150](https://www.permitgraph.org/p/202002114150) | Feb 11, 2020 | Completed: final sign-off Nov 2021 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Sign Of Light](https://www.permitgraph.org/contractor/sign-of-light-906191) | install 1 non-illuminated decal/window signage "nesspresso" | $2,000 |
| [202002114143](https://www.permitgraph.org/p/202002114143) | Feb 11, 2020 | Completed: final sign-off Apr 2021 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Michilli Inc](https://www.permitgraph.org/contractor/michilli-inc-946443) | "nespresso" interior ti for retail on g/f space of (e) bldg, install new cladding over (e) storefront framing, reconfigure interior partitions, new hvac systems, lighting, plumbing & interior finishe… | $800,000 |
| [202002114159](https://www.permitgraph.org/p/202002114159) | Feb 11, 2020 | Completed: final sign-off Nov 2021 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Sign Of Light](https://www.permitgraph.org/contractor/sign-of-light-906191) | install 1 illuminated double-faced projecting blade sign "nesspresso" | $2,000 |
| [201908078132](https://www.permitgraph.org/p/201908078132) | Aug 7, 2019 | Never finaled: issued Aug 2019, no final | [55 Stockton St](https://www.permitgraph.org/a/0327/002) |  | 4th fl fire evacuation plan x4 | $2,500 |
| [201908057837](https://www.permitgraph.org/p/201908057837) | Aug 5, 2019 | Completed: final sign-off Apr 2026 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Red Hawk Fire & Security Ca Llc](https://www.permitgraph.org/contractor/red-hawk-fire-security-ca-llc-713099) | 4th fl - 2 way communication wrath 2 way communication head end in fcc 2 call boxes. ref pa 2019-0416-8103 | $15,000 |
| [201907236583](https://www.permitgraph.org/p/201907236583) | Jul 23, 2019 | Completed: final sign-off Sep 2019 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Paradigm General Contractors](https://www.permitgraph.org/contractor/paradigm-general-contractors-608135) | 4th fl - revision to pa 2019-0416-8103 adding a sink in women's room accessible stall |  |
| [201906214104](https://www.permitgraph.org/p/201906214104) | Jun 21, 2019 | Completed: final sign-off Aug 2019 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Red Hawk Fire & Security Ca Llc](https://www.permitgraph.org/contractor/red-hawk-fire-security-ca-llc-713099) | scope: 4th fl add 20 speaker strobes, add 5 strobes | $12,000 |
| [201906193826](https://www.permitgraph.org/p/201906193826) | Jun 19, 2019 | Completed: final sign-off Aug 2019 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) |  | 4th flr. fire sprinkler permit. relocate 69, add 12 and delete 15 sprinklers. ref t.i 201904168103. | $21,000 |
| [201904309258](https://www.permitgraph.org/p/201904309258) | Apr 30, 2019 | Completed: final sign-off Oct 2019 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Paradigm General Contractors](https://www.permitgraph.org/contractor/paradigm-general-contractors-608135) | 4th fl - meps for 2019-0416-8103 | $500,000 |
| [201904168103](https://www.permitgraph.org/p/201904168103) | Apr 16, 2019 | Completed: final sign-off Sep 2019 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Paradigm General Contractors](https://www.permitgraph.org/contractor/paradigm-general-contractors-608135) | 4th fl ti demo of on structural partitions and buildin new non str partitions. mep under separate permit, life safety and sprinkler under sep permit. bldg is fully sprinklered | $480,000 |
| [201604296183](https://www.permitgraph.org/p/201604296183) | Apr 29, 2016 | Completed: final sign-off Jun 2016 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [San Francisco Commercial Builders Inc](https://www.permitgraph.org/contractor/san-francisco-commercial-builders-inc-801883) | construct approx 49 l.f. non-bearing partition. install millwork, cabinetry, finishes. refinish extg floor. install outlets. no lighting add or alteration point. | $150,000 |
| [201604154931](https://www.permitgraph.org/p/201604154931) | Apr 15, 2016 | Expired or cancelled: cancelled Jun 2019 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Red Hawk Fire & Security Ca Llc](https://www.permitgraph.org/contractor/red-hawk-fire-security-ca-llc-713099) | lower level: fire alarm t.i. relocating (2) eixsting speaker/strobes, increase candela rating on 91) existing speaker/strobes. | $1,500 |
| [201403251578](https://www.permitgraph.org/p/201403251578) | Mar 25, 2014 | Never finaled: issued Aug 2014, no final | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Northwest Signs](https://www.permitgraph.org/contractor/northwest-signs-786185) | erect a non-electric double faced projecting sign | $7,500 |
| [201310290484](https://www.permitgraph.org/p/201310290484) | Oct 29, 2013 | Completed: final sign-off Jan 2014 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Hawk Mechanical Inc](https://www.permitgraph.org/contractor/hawk-mechanical-inc-822098) | relocate 1 heat pump with duct work & grilles, relocate 3 vav boxes with duct work & grilles, relocate 1 ft box with duct work and grilles, relocate 2 exhaust fans with duct work & grilles, install 3… | $37,000 |
| [201307303068](https://www.permitgraph.org/p/201307303068) | Jul 30, 2013 | Completed: final sign-off Sep 2013 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Red Hawk Fire & Security Ca Llc](https://www.permitgraph.org/contractor/red-hawk-fire-security-ca-llc-713099) | 4/f- t.i. scope of work. new devices to be added to the extg fire alarm. total of 11 speaker/strobes. | $5,000 |
| [201307292965](https://www.permitgraph.org/p/201307292965) | Jul 29, 2013 | Completed: final sign-off Aug 2013 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Golden Gate Fire Protection Inc](https://www.permitgraph.org/contractor/golden-gate-fire-protection-inc-960198) | 4th floor-relocate 27 upright sprinklers on the 4th floor. relocate 9 pendent sprinkler heads | $18,540 |
| [201305247835](https://www.permitgraph.org/p/201305247835) | May 24, 2013 | Completed: final sign-off Dec 2013 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [San Francisco Commercial Builders Inc](https://www.permitgraph.org/contractor/san-francisco-commercial-builders-inc-801883) | tenant improvement including demo, new partitions, mill work, lighting, electrical & data, minor plumbing. mep, fire, life safety under separate permit. | $140,000 |
| [M386907](https://www.permitgraph.org/p/M386907) | Apr 19, 2013 | Never finaled: issued Apr 2013, no final | [55 Stockton St](https://www.permitgraph.org/a/0327/002) |  | street space |  |
| [201209179927](https://www.permitgraph.org/p/201209179927) | Sep 17, 2012 | Completed: final sign-off Sep 2012 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) |  | fire sprinkler only. relocate 11 heads; add 6 heads & remove 3 heads. total of 17 heads for apple store break room of back of house (remote). t.i. pa# 201206192955. | $8,500 |
| [201208278268](https://www.permitgraph.org/p/201208278268) | Aug 27, 2012 | Never finaled: issued Aug 2012, no final | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Red Hawk Fire & Security Ca Llc](https://www.permitgraph.org/contractor/red-hawk-fire-security-ca-llc-713099) | lower level 2 - fire alarm system, add 4 duct detectors, add 4 control relays, add 12 speaker/strobes. ref. to app#2012-06-19-2955. | $15,000 |
| [201208157459](https://www.permitgraph.org/p/201208157459) | Aug 15, 2012 | Never finaled: issued Aug 2012, no final | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Rudolph And Sletten Inc](https://www.permitgraph.org/contractor/rudolph-and-sletten-inc-198069) | enlarge office room on second level basement. relocate lockers, remove break station. remove acoustic ceiling panels in manager and hr office | $25,000 |
| [201206192955](https://www.permitgraph.org/p/201206192955) | Jun 19, 2012 | Completed: final sign-off Sep 2012 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Rudolph And Sletten Inc](https://www.permitgraph.org/contractor/rudolph-and-sletten-inc-198069) | basement level-t.i. of (e) office space, work to include non structural partitions, ceilings, finishes, furniture & m.e.p | $170,000 |
| [201109084140](https://www.permitgraph.org/p/201109084140) | Sep 8, 2011 | Completed: final sign-off Jan 2012 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Pacific Coast Trane Service Co.](https://www.permitgraph.org/contractor/pacific-coast-trane-service-co-465656) | roof area. replacement of outside air unit (hvac) | $70,000 |
| [201103242729](https://www.permitgraph.org/p/201103242729) | Mar 24, 2011 | Completed: final sign-off Jul 2011 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Diversified Fire Products](https://www.permitgraph.org/contractor/diversified-fire-products-627565) | fire alarm ti at 55 stockton ll2: 2 new smoke detectors, 1 new speaker strobe | $3,233 |
| [201103091718](https://www.permitgraph.org/p/201103091718) | Mar 9, 2011 | Completed: final sign-off Apr 2011 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Potter Fire Protection](https://www.permitgraph.org/contractor/potter-fire-protection-338830) | lower level-relocate 3 sprinklers and associated piping from above new switch gear equipment | $1,750 |
| [201102180598](https://www.permitgraph.org/p/201102180598) | Feb 18, 2011 | Completed: final sign-off Sep 2011 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) | [Arrow Sign Company](https://www.permitgraph.org/contractor/arrow-sign-company-314794) | to erect electric, projecting, double faced sign. | $7,000 |
| [200008168101](https://www.permitgraph.org/p/200008168101) | Aug 16, 2000 | Completed: final sign-off Feb 2001 | [55 Stockton St](https://www.permitgraph.org/a/0327/002) |  | revision to 2000/04/18/7539. relocate panels&smoke removal fan, reloc fire pump generator exhaust | $40,000 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Paradigm General Contractors](https://www.permitgraph.org/contractor/paradigm-general-contractors-608135) (13), [Everon Llc](https://www.permitgraph.org/contractor/everon-llc-1065604) (6), [Red Hawk Fire & Security Ca Llc](https://www.permitgraph.org/contractor/red-hawk-fire-security-ca-llc-713099) (5), [Urban Graphics Inc](https://www.permitgraph.org/contractor/urban-graphics-inc-1078591) (3), [Rudolph And Sletten Inc](https://www.permitgraph.org/contractor/rudolph-and-sletten-inc-198069) (2), [San Francisco Commercial Builders Inc](https://www.permitgraph.org/contractor/san-francisco-commercial-builders-inc-801883) (2), [Sign Of Light](https://www.permitgraph.org/contractor/sign-of-light-906191) (2), [Thomas Swan Sign Co Inc](https://www.permitgraph.org/contractor/thomas-swan-sign-co-inc-269069) (2), [Arrow Sign Company](https://www.permitgraph.org/contractor/arrow-sign-company-314794), [Big Joe California North Inc](https://www.permitgraph.org/contractor/big-joe-california-north-inc-931417), [C B F Inc](https://www.permitgraph.org/contractor/c-b-f-inc-335873), [Diversified Fire Products](https://www.permitgraph.org/contractor/diversified-fire-products-627565), [Golden Gate Fire Protection Inc](https://www.permitgraph.org/contractor/golden-gate-fire-protection-inc-960198), [Hawk Mechanical Inc](https://www.permitgraph.org/contractor/hawk-mechanical-inc-822098), [Martin Sign Co Inc.](https://www.permitgraph.org/contractor/martin-sign-co-inc-980058), [Michilli Inc](https://www.permitgraph.org/contractor/michilli-inc-946443), [Northwest Signs](https://www.permitgraph.org/contractor/northwest-signs-786185), [Pacific Coast Trane Service Co.](https://www.permitgraph.org/contractor/pacific-coast-trane-service-co-465656), [Pioneer Fire Inc.](https://www.permitgraph.org/contractor/pioneer-fire-inc-927862), [Potter Fire Protection](https://www.permitgraph.org/contractor/potter-fire-protection-338830)
- Architects: [Ariane Lebrilla](https://www.permitgraph.org/professional/ariane-lebrilla-C38312) (7), [James Goring](https://www.permitgraph.org/professional/james-goring-C19278) (3), [Joseph Remling](https://www.permitgraph.org/professional/joseph-remling-C34144) (2), [Stanley H Lew](https://www.permitgraph.org/professional/stanley-h-lew-C29609) (2), [Joel Karr](https://www.permitgraph.org/professional/joel-karr-C29051), [Peter Petruzzi](https://www.permitgraph.org/professional/peter-petruzzi-C18480)
- Engineers: [Stephen Shafeer](https://www.permitgraph.org/professional/stephen-shafeer-E21097) (3), [Angela Faught](https://www.permitgraph.org/professional/angela-faught-E22866) (2), [Brandon Elliott](https://www.permitgraph.org/professional/brandon-elliott-M38639) (2), [Pablo Orozco](https://www.permitgraph.org/professional/pablo-orozco-M27485) (2), [Steven Curry](https://www.permitgraph.org/professional/steven-curry-S3364) (2), [Carl Milsum](https://www.permitgraph.org/professional/carl-milsum-S6190), [Kylie Lo](https://www.permitgraph.org/professional/kylie-lo-E23357), [Meng Hsiu Chen](https://www.permitgraph.org/professional/meng-hsiu-chen-M19582), [Peter Kogan](https://www.permitgraph.org/professional/peter-kogan-24758), [Robert Vancamp](https://www.permitgraph.org/professional/robert-vancamp-84506)
- Authorized agents: [David Raun](https://www.permitgraph.org/professional/david-raun-777717), [Erika M Yanez](https://www.permitgraph.org/professional/erika-m-yanez-608135)
- Designers: [Martin Page Wall](https://www.permitgraph.org/professional/martin-page-wall-980058), [R L H Fire Protection Inc](https://www.permitgraph.org/professional/r-l-h-fire-protection-inc-777717)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/a/0327/002.