# 411 Ofarrell St

Block 0324, lot 001. Page: https://www.permitgraph.org/a/0324/001

- City's use: Commercial Hotel
- Built: 1910
- Stories: 6
- Units: 6
- Rooms: 82 bathrooms
- Building: 41,610 sq ft
- Lot: 6,372 sq ft
- Zoning: RC4
- Construction type: C

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

21 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [201901301635](https://www.permitgraph.org/p/201901301635) | Jan 30, 2019 | Never finaled: issued Jan 2019, no final | [411 Ofarrell St](https://www.permitgraph.org/a/0324/001) | [San Francisco Fire Protection](https://www.permitgraph.org/contractor/san-francisco-fire-protection-806216) | as builts to app#201803133511. add 2 extg notification appliances on ground floor and tie-in to extg control panel. maher n/a. |  |
| [201901100037](https://www.permitgraph.org/p/201901100037) | Jan 10, 2019 | Never finaled: issued Jan 2019, no final | [411 Ofarrell St](https://www.permitgraph.org/a/0324/001) | [San Francisco Fire Protection](https://www.permitgraph.org/contractor/san-francisco-fire-protection-806216) | t.i. to install new power supply panel and smoke detector above on 2nd, 4th, & 6th floors. install low frequency sounder in every room to meet new sffd. sec. 1103.7.6.1 and tie-in to new power supply… | $27,500 |
| [201803133511](https://www.permitgraph.org/p/201803133511) | Mar 13, 2018 | Never finaled: issued Mar 2018, no final | [411 O'farrell St](https://www.permitgraph.org/a/0324/001) | [San Francisco Fire Protection](https://www.permitgraph.org/contractor/san-francisco-fire-protection-806216) | like for like fire system replacement w/upgrade elevator modernization w/new panel smoke detector & pull stations at the same location. existing bells will be tie-in to new panel. new smoke detectors… | $18,000 |
| [201801249437](https://www.permitgraph.org/p/201801249437) | Jan 24, 2018 | Completed: final sign-off Mar 2019 | [411 Ofarrell St](https://www.permitgraph.org/a/0324/001) | [Taico Builder Inc](https://www.permitgraph.org/contractor/taico-builder-inc-986586) | revision to 201603313666 ada restroom revision only maher na |  |
| [201801178823](https://www.permitgraph.org/p/201801178823) | Jan 17, 2018 | Expired or cancelled: cancelled Jan 2026 | [411 O'farrell St](https://www.permitgraph.org/a/0324/001) | [B B J Electric, Inc](https://www.permitgraph.org/contractor/b-b-j-electric-inc-670906) | modify elevator door openings. no stuctural work. maher not req | $48,000 |
| [201712227292](https://www.permitgraph.org/p/201712227292) | Dec 22, 2017 | Completed: final sign-off Oct 2018 | [411 Ofarrell St](https://www.permitgraph.org/a/0324/001) | [Taico Builder Inc](https://www.permitgraph.org/contractor/taico-builder-inc-986586) | new store front upgrade. maher n/a | $20,000 |
| [201611092364](https://www.permitgraph.org/p/201611092364) | Nov 9, 2016 | Expired or cancelled: cancelled Jan 2026 | [407 Ofarrell St](https://www.permitgraph.org/a/0324/001) |  | tenant improvement for vacant store to become a sandwich shop. mep deferred permit. maher na | $35,000 |
| [201603313666](https://www.permitgraph.org/p/201603313666) | Mar 31, 2016 | Completed: final sign-off Mar 2019 | [411 Ofarrell St](https://www.permitgraph.org/a/0324/001) | [Taico Builder Inc](https://www.permitgraph.org/contractor/taico-builder-inc-986586) | to comply with nov 201254442: interior work only: remodel (e) hoste lobby on ground floor. relocate (e) ada restroom. voluntary upgrade of stair handrail from lobby to mezzanine level. fire/mep - und… | $100,000 |
| [201409126171](https://www.permitgraph.org/p/201409126171) | Sep 12, 2014 | Completed: final sign-off Mar 2019 | [411 Ofarrell St](https://www.permitgraph.org/a/0324/001) | [Del Smith Design Build](https://www.permitgraph.org/contractor/del-smith-design-build-923616) | tenant improvement to (e) 759 s.f. enclosed mezzanine space located behind double height lobby in youth hostel - work to include removal of interior partiiton & construction of interior millwork proj… | $50,000 |
| [201308023393](https://www.permitgraph.org/p/201308023393) | Aug 2, 2013 | Never finaled: issued Aug 2013, no final | [411 O'farrell St](https://www.permitgraph.org/a/0324/001) | [S.F.A-1 Roofing & Maintenance](https://www.permitgraph.org/contractor/s-f-a-1-roofing-maintenance-742662) | reroofing | $25,500 |
| [201304184928](https://www.permitgraph.org/p/201304184928) | Apr 18, 2013 | Never finaled: issued May 2013, no final | [411 O'farrell St](https://www.permitgraph.org/a/0324/001) |  | installing grab bars, community bathrooms, min. rating of 250 lbs, installing telephone jacks |  |
| [201210232672](https://www.permitgraph.org/p/201210232672) | Oct 23, 2012 | Expired or cancelled: cancelled Jan 2026 | [405 Ofarrell St](https://www.permitgraph.org/a/0324/001) |  | abate nov 2012654442. legalize atm at store front of ofarrell and taylor | $1,500 |
| [201210091522](https://www.permitgraph.org/p/201210091522) | Oct 9, 2012 | Never finaled: issued Oct 2012, no final | [385 Taylor St](https://www.permitgraph.org/a/0324/001) | [Peninsula Fire Protection Inc](https://www.permitgraph.org/contractor/peninsula-fire-protection-inc-839602) | upgrade fire suppression system to comply with ul 300 standards. extg 9'-6" hood and duct. | $4,500 |
| [M349287](https://www.permitgraph.org/p/M349287) | Sep 21, 2012 | Never finaled: issued Sep 2012, no final | [385 Taylor St](https://www.permitgraph.org/a/0324/001) |  | street space & mta |  |
| [201208137250](https://www.permitgraph.org/p/201208137250) | Aug 13, 2012 | Never finaled: issued Aug 2012, no final | [385 Taylor St](https://www.permitgraph.org/a/0324/001) | [Galaxy Building Construction](https://www.permitgraph.org/contractor/galaxy-building-construction-892100) | resize and alter store front and upgrade front door to comply with ada requirements | $10,000 |
| [M62026](https://www.permitgraph.org/p/M62026) | Mar 28, 2007 | Never finaled: issued Mar 2007, no final | [411 Ofarrell St](https://www.permitgraph.org/a/0324/001) |  | street space |  |
| [M60608](https://www.permitgraph.org/p/M60608) | Mar 15, 2007 | Never finaled: issued Mar 2007, no final | [411 Ofarrell St](https://www.permitgraph.org/a/0324/001) |  | street space permit only. |  |
| [200507016685](https://www.permitgraph.org/p/200507016685) | Jul 1, 2005 | Never finaled: issued Jul 2005, no final | [411 Ofarrell St](https://www.permitgraph.org/a/0324/001) | [San Francisco Fire Protection](https://www.permitgraph.org/contractor/san-francisco-fire-protection-806216) | monitor new water flow devices | $4,000 |
| [200409224861](https://www.permitgraph.org/p/200409224861) | Sep 22, 2004 | Completed: final sign-off Oct 2005 | [411 O'farrell St](https://www.permitgraph.org/a/0324/001) | [Fire Protection Retrofit Specialist](https://www.permitgraph.org/contractor/fire-protection-retrofit-specialist-638976) | to install fire sprinkler system to comply with ord#170-02. | $63,000 |
| [200309296041](https://www.permitgraph.org/p/200309296041) | Sep 29, 2003 | Never finaled: issued May 2004, no final | [411 Ofarrell St](https://www.permitgraph.org/a/0324/001) | [Mazzys Fire Protection](https://www.permitgraph.org/contractor/mazzys-fire-protection-502015) | system upgrade fire sprinklers for sro | $40,000 |
| [200008238709](https://www.permitgraph.org/p/200008238709) | Aug 23, 2000 | Expired or cancelled: expired Apr 2001 | [411 O'farrell St](https://www.permitgraph.org/a/0324/001) |  | install partition wall to separate offices and hotel lobby. | $4,500 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [San Francisco Fire Protection](https://www.permitgraph.org/contractor/san-francisco-fire-protection-806216) (4), [Taico Builder Inc](https://www.permitgraph.org/contractor/taico-builder-inc-986586) (3), [B B J Electric, Inc](https://www.permitgraph.org/contractor/b-b-j-electric-inc-670906), [Del Smith Design Build](https://www.permitgraph.org/contractor/del-smith-design-build-923616), [Fire Protection Retrofit Specialist](https://www.permitgraph.org/contractor/fire-protection-retrofit-specialist-638976), [Galaxy Building Construction](https://www.permitgraph.org/contractor/galaxy-building-construction-892100), [Mazzys Fire Protection](https://www.permitgraph.org/contractor/mazzys-fire-protection-502015), [Peninsula Fire Protection Inc](https://www.permitgraph.org/contractor/peninsula-fire-protection-inc-839602), [S.F.A-1 Roofing & Maintenance](https://www.permitgraph.org/contractor/s-f-a-1-roofing-maintenance-742662)
- Architects: [Charles Chan](https://www.permitgraph.org/professional/charles-chan-C31716) (2), [Michael Mccall](https://www.permitgraph.org/professional/michael-mccall-C15502)
- Engineers: [Charles Chan](https://www.permitgraph.org/professional/charles-chan-C31716), [John Lau](https://www.permitgraph.org/professional/john-lau-188881), [Luis Antonio Robles](https://www.permitgraph.org/professional/luis-antonio-robles-C21700)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/a/0324/001.