# 901 Pine St

Block 0274, lot 024. Page: https://www.permitgraph.org/a/0274/024

- City's use: Multi-Family Residential
- Built: 1908
- Stories: 4
- Units: 36
- Rooms: 30 bedrooms, 36 bathrooms
- Building: 29,610 sq ft
- Lot: 7,931 sq ft
- Zoning: RM4
- Construction type: D

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

44 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [202601053244](https://www.permitgraph.org/p/202601053244) | Jan 5, 2026 | In progress: issued Jan 2026 | [901 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | to obtain final inspection for work approved under pa# 202411064518. all work is complete. |  |
| [202501138204](https://www.permitgraph.org/p/202501138204) | Jan 13, 2025 | Completed: final sign-off Mar 2025 | [901 Pine St](https://www.permitgraph.org/a/0274/024) | [All Systems Approved Inc](https://www.permitgraph.org/contractor/all-systems-approved-inc-1040375) | unit 10- revision 202410233544 and ref 202412056246- as built relocate fire sprinkler line layout - add (1) sprinkler head |  |
| [202412056246](https://www.permitgraph.org/p/202412056246) | Dec 5, 2024 | Completed: final sign-off Mar 2025 | [901 Pine St](https://www.permitgraph.org/a/0274/024) | [All Systems Approved Inc](https://www.permitgraph.org/contractor/all-systems-approved-inc-1040375) | revision 202410233544- add (3) sprinkler heads to the new closet space |  |
| [202411064518](https://www.permitgraph.org/p/202411064518) | Nov 6, 2024 | In progress: issued Nov 2024 | [901 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | revision to pa # 2022-1223-9112 revise fire sprinkler specification from (e) nfpa 13 to (e) nfpa 13r. provide nfpa 13r fire sprinkler system at proposed unit |  |
| [202410233544](https://www.permitgraph.org/p/202410233544) | Oct 23, 2024 | Completed: final sign-off Mar 2025 | [901 Pine St](https://www.permitgraph.org/a/0274/024) | [All Systems Approved Inc](https://www.permitgraph.org/contractor/all-systems-approved-inc-1040375) | augment an nfpa 13r, automatic, wet pipe, fire sprinkler system in a 4 story building plus basement on the 1st floor unit #10. ref pa# 202212239112 | $8,462 |
| [202409050144](https://www.permitgraph.org/p/202409050144) | Sep 5, 2024 | Completed: final sign-off Oct 2024 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Bkr Services Inc Dba Bkr Construction Se](https://www.permitgraph.org/contractor/bkr-services-inc-dba-bkr-construction-se-1031979) | apt 2: remodel ktichen: new cabinets & new tile floor. | $45,000 |
| [202406285543](https://www.permitgraph.org/p/202406285543) | Jun 28, 2024 | In progress: issued Jul 2024 | [901 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | revision to pa 202212239112 revise concrete footings and wood beams |  |
| [202404049301](https://www.permitgraph.org/p/202404049301) | Apr 4, 2024 | Completed: final sign-off May 2024 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Au Electric Corporation/Aec Alarms](https://www.permitgraph.org/contractor/au-electric-corporation-aec-alarms-381840) | rev 202305047089- as built per fire inspector - install (1) pull station on ifc side (e) hallway, install (1) monitor module for valve tamper supervisory, remove (2) relay modules, no connection is n… |  |
| [202403228423](https://www.permitgraph.org/p/202403228423) | Mar 22, 2024 | Completed: final sign-off Jul 2024 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Bkr Services Inc Dba Bkr Construction Se](https://www.permitgraph.org/contractor/bkr-services-inc-dba-bkr-construction-se-1031979) | unit #31: convert existing kitchen to office. relocate kitchen, rehabilitate existing bathroom. install washer and dryer. | $60,000 |
| [202401224344](https://www.permitgraph.org/p/202401224344) | Jan 22, 2024 | Completed: final sign-off Feb 2024 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Bkr Services Inc Dba Bkr Construction Se](https://www.permitgraph.org/contractor/bkr-services-inc-dba-bkr-construction-se-1031979) | unit 18: amend permit pa# 202312041873 to add plans, moving the kitchen location |  |
| [202312041873](https://www.permitgraph.org/p/202312041873) | Dec 4, 2023 | Completed: final sign-off Feb 2024 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Bkr Services Inc Dba Bkr Construction Se](https://www.permitgraph.org/contractor/bkr-services-inc-dba-bkr-construction-se-1031979) | #18. kitchen remodel upgrade plumbing and electrical to service new kitchen layout. no changes to the wall layout. | $40,000 |
| [202306220605](https://www.permitgraph.org/p/202306220605) | Jun 22, 2023 | Completed: final sign-off Oct 2023 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | unit 22: convert e kitchen to office, relocate kitchen. rehabilitate e bath, install washer dryer | $70,000 |
| [202305047089](https://www.permitgraph.org/p/202305047089) | May 4, 2023 | Never finaled: issued May 2023, no final | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Au Electric Corporation/Aec Alarms](https://www.permitgraph.org/contractor/au-electric-corporation-aec-alarms-381840) | upgrade (e) f/a system to comply w/sffc 1103.7.6.1, install wireless low freq sounders in all sleeping areas, like-for-like replacements for (e) pull, smoke, horn/strobes in common areas. | $75,000 |
| [202301250744](https://www.permitgraph.org/p/202301250744) | Jan 25, 2023 | Completed: final sign-off Oct 2023 | [901 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | convert 218 sf storage room @ basement into (n) 209 sf trash room, no changes to the exterior | $10,000 |
| [202301190411](https://www.permitgraph.org/p/202301190411) | Jan 19, 2023 | Never finaled: issued Jan 2023, no final | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | unit #17, 27, 37, 47: project scope consist of stacked load bearing walls demolition. provide (n) post & beams and post to foundation. | $5,000 |
| [202212239112](https://www.permitgraph.org/p/202212239112) | Dec 23, 2022 | In progress: issued Feb 2024 | [901 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | legalization of(e)unit @ 901 pine street,per ordinance 43-14(convert former commercial space into residential unit).reconfigure(e)unit to become a 860 sf 2-bedroom unit.(e)sprinkler system to be modi… | $60,000 |
| [202211237111](https://www.permitgraph.org/p/202211237111) | Nov 23, 2022 | Completed: final sign-off Mar 2023 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | unit 32: convert (e) kitchen to office. relocate kitchen. rehab (e) bathroom. install washer and dryer. | $32,000 |
| [202211025773](https://www.permitgraph.org/p/202211025773) | Nov 2, 2022 | Completed: final sign-off Jun 2023 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | #24: rehab (e) kitchen, rehab (e) bathroom. install washer/dryer. no structural wall demo. | $28,000 |
| [202211025777](https://www.permitgraph.org/p/202211025777) | Nov 2, 2022 | Completed: final sign-off Jun 2023 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | unit 15: convert (e) living rm to bedroom. rehab (e) kitchen & bath. install washer/dryer. incorporate (e) manager office into (e) unit 15. | $42,000 |
| [202210214904](https://www.permitgraph.org/p/202210214904) | Oct 21, 2022 | Completed: final sign-off Apr 2023 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | #17 - 1st flr: convert (e) kitchen to study. relocated kitchen. rehab (e) bathroom. install washer/gas dryer. | $34,000 |
| [202210214924](https://www.permitgraph.org/p/202210214924) | Oct 21, 2022 | Completed: final sign-off Jun 2023 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | 47: convert (e) kitchen to bedroom. relocate kitchen. rehab (e) bathroom. install washer/dryer. | $34,000 |
| [202210214901](https://www.permitgraph.org/p/202210214901) | Oct 21, 2022 | Completed: final sign-off Apr 2023 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | unit 27 - 2nd flr: convert (e) kitchen to study. relocate kitchen. rehab (e) bathroom. install washer/gas dryer. | $34,000 |
| [202210214921](https://www.permitgraph.org/p/202210214921) | Oct 21, 2022 | Completed: final sign-off Jun 2023 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | #37: convert (e) kitchen to study. relocate kitchen. rehab (e) bathroom. install washer/dryer. | $34,000 |
| [202210174458](https://www.permitgraph.org/p/202210174458) | Oct 17, 2022 | Completed: final sign-off Jun 2023 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | unit 6 - convert (e) kitchen to study room; relocate kitchen, rehabilitate existing bathroom; install washer and dryer; install 2nd bathroom | $45,000 |
| [202210174477](https://www.permitgraph.org/p/202210174477) | Oct 17, 2022 | Completed: final sign-off Jun 2023 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | unit 41: convert existing kitchen to office. relocate kitchen. rehabilitate existing bathroom. install washer and dryer. | $32,000 |
| [202210174457](https://www.permitgraph.org/p/202210174457) | Oct 17, 2022 | Completed: final sign-off Jun 2023 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | unit 46 - convert (e) kitchen to bedroom; relocate kitchen, rehabilitate existing bathroom; install washer and dryer | $32,000 |
| [202210174475](https://www.permitgraph.org/p/202210174475) | Oct 17, 2022 | Expired or cancelled: cancelled Dec 2022 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | unit 31: convert existing kitchen to office. relocate kitchen. rehabilitate existing bathroom. install washer and dryer. | $32,000 |
| [202209293418](https://www.permitgraph.org/p/202209293418) | Sep 29, 2022 | Completed: final sign-off Jul 2023 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | unit 33: rehab (e) kitchen, (e) bathroom, install washer/dryer | $40,000 |
| [202209293416](https://www.permitgraph.org/p/202209293416) | Sep 29, 2022 | Completed: final sign-off Jul 2023 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | unit 23: rehab (e) kitchen, (e) bathroom, install washer/dryer | $40,000 |
| [202209293400](https://www.permitgraph.org/p/202209293400) | Sep 29, 2022 | Completed: final sign-off Dec 2022 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) | unit 14: install washer and dryer. no wall demo. | $5,000 |
| [201502047458](https://www.permitgraph.org/p/201502047458) | Feb 4, 2015 | Never finaled: issued Feb 2015, no final | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [All Fusion Construction Inc](https://www.permitgraph.org/contractor/all-fusion-construction-inc-968019) | revision to 201412294585 - not remodelling unit 42 (deleted work on unit #42) |  |
| [201412294585](https://www.permitgraph.org/p/201412294585) | Dec 29, 2014 | Never finaled: issued Dec 2014, no final | [901 Pine St](https://www.permitgraph.org/a/0274/024) | [All Fusion Construction Inc](https://www.permitgraph.org/contractor/all-fusion-construction-inc-968019) | remodel unit 45 & 42 bathroom kitchen plumbing electrical - no structural work. no wall modification, finishes only. including appliances, fixturs, cabinetry | $20,000 |
| [201412194191](https://www.permitgraph.org/p/201412194191) | Dec 19, 2014 | Completed: final sign-off Apr 2015 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Young's Roofing, Inc.](https://www.permitgraph.org/contractor/young-s-roofing-inc-675687) | to obtain final inspection for work approved under pa# 200703125959. all work is complete. |  |
| [M538287](https://www.permitgraph.org/p/M538287) | Nov 18, 2014 | Never finaled: issued Nov 2014, no final | [901 Pine St](https://www.permitgraph.org/a/0274/024) |  | street space |  |
| [201410280063](https://www.permitgraph.org/p/201410280063) | Oct 28, 2014 | Completed: final sign-off Nov 2014 | [901 Pine St](https://www.permitgraph.org/a/0274/024) | [All Fusion Construction Inc](https://www.permitgraph.org/contractor/all-fusion-construction-inc-968019) | change 6 windows in unit #46. not visible from the street. comply with nov #201343811. items 2 & 3. u factor 0.32 max | $2,200 |
| [201410169124](https://www.permitgraph.org/p/201410169124) | Oct 16, 2014 | Completed: final sign-off Jul 2015 | [901 Pine St](https://www.permitgraph.org/a/0274/024) | [All Fusion Construction Inc](https://www.permitgraph.org/contractor/all-fusion-construction-inc-968019) | comply with notice of violation complaints 201343811 replace 250 windows. paint exterior. all windows at the visible facades shal be replaced with wood single hung windows to fit existing openings an… | $130,000 |
| [200708028614](https://www.permitgraph.org/p/200708028614) | Aug 2, 2007 | Completed: final sign-off Aug 2007 | [903 Pine St](https://www.permitgraph.org/a/0274/024) |  | renew 200610255984 for final inpsection only |  |
| [200703125959](https://www.permitgraph.org/p/200703125959) | Mar 12, 2007 | Never finaled: issued Mar 2007, no final | [901 Pine St](https://www.permitgraph.org/a/0274/024) | [Young's Roofing, Inc.](https://www.permitgraph.org/contractor/young-s-roofing-inc-675687) | reroofing | $20,500 |
| [200610255984](https://www.permitgraph.org/p/200610255984) | Oct 25, 2006 | Expired or cancelled: expired Aug 2007 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [New Era Construction Co. ***Check Id****](https://www.permitgraph.org/contractor/new-era-construction-co-check-id-420893) | interior remodel unit#47 at 903 pine st. to comply with nov#200679713 (bid) . remodel kitchen and full bath with replacement of cabinets and fixtures. no change to wall and window. no structural chan… | $10,000 |
| [M33773](https://www.permitgraph.org/p/M33773) | Aug 9, 2005 | Never finaled: issued Aug 2005, no final | [901 Pine St](https://www.permitgraph.org/a/0274/024) |  | street space |  |
| [M32070](https://www.permitgraph.org/p/M32070) | Apr 15, 2005 | Never finaled: issued Apr 2005, no final | [903 Pine St](https://www.permitgraph.org/a/0274/024) |  | street space |  |
| [200412201820](https://www.permitgraph.org/p/200412201820) | Dec 20, 2004 | Completed: final sign-off Nov 2005 | [903 Pine St](https://www.permitgraph.org/a/0274/024) | [Har Bro Of No. California](https://www.permitgraph.org/contractor/har-bro-of-no-california-736982) | fire repair of elevator shaft and adjoinging area | $40,000 |
| [200412171653](https://www.permitgraph.org/p/200412171653) | Dec 17, 2004 | Never finaled: issued Dec 2004, no final | [755 Mason St](https://www.permitgraph.org/a/0274/024) | [Young's Roofing, Inc.](https://www.permitgraph.org/contractor/young-s-roofing-inc-675687) | reroofing | $9,000 |
| [M15218](https://www.permitgraph.org/p/M15218) | Dec 27, 2000 | Expired or cancelled: expired Apr 2001 | [901 Pine St](https://www.permitgraph.org/a/0274/024) |  | sidewalk |  |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Axel8 Construction](https://www.permitgraph.org/contractor/axel8-construction-1045139) (21), [All Fusion Construction Inc](https://www.permitgraph.org/contractor/all-fusion-construction-inc-968019) (4), [Bkr Services Inc Dba Bkr Construction Se](https://www.permitgraph.org/contractor/bkr-services-inc-dba-bkr-construction-se-1031979) (4), [All Systems Approved Inc](https://www.permitgraph.org/contractor/all-systems-approved-inc-1040375) (3), [Young's Roofing, Inc.](https://www.permitgraph.org/contractor/young-s-roofing-inc-675687) (3), [Au Electric Corporation/Aec Alarms](https://www.permitgraph.org/contractor/au-electric-corporation-aec-alarms-381840) (2), [Har Bro Of No. California](https://www.permitgraph.org/contractor/har-bro-of-no-california-736982), [New Era Construction Co. ***Check Id****](https://www.permitgraph.org/contractor/new-era-construction-co-check-id-420893)
- Architects: [Joe Kon](https://www.permitgraph.org/professional/joe-kon-C65772) (2), [Serina Calhoun](https://www.permitgraph.org/professional/serina-calhoun-C30744) (2)
- Engineers: [Joe Win Kon](https://www.permitgraph.org/professional/joe-win-kon-S5425) (15), [Darren Wong](https://www.permitgraph.org/professional/darren-wong-C81082), [Darren Wong](https://www.permitgraph.org/professional/darren-wong-81082)
- Authorized agents: [Roger Tsai](https://www.permitgraph.org/professional/roger-tsai-381840), [Serina Calhoun](https://www.permitgraph.org/professional/serina-calhoun-C30744)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/a/0274/024.