# 601 Jackson St

Block 0194, lot 001. Page: https://www.permitgraph.org/a/0194/001

- City's use: Commercial Office
- Lot: 2,339 sq ft
- Zoning: CCB
- Construction type: NA

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

21 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [202403147786](https://www.permitgraph.org/p/202403147786) | Mar 14, 2024 | Completed: final sign-off Dec 2024 | [601 Jackson St](https://www.permitgraph.org/a/0194/001) | [Paradise Construction](https://www.permitgraph.org/contractor/paradise-construction-1101815) | replace 4 penthouse anodized alm. gl. with anodized alum. gl. windows match adjacent extg windows finishes & sill hts. windows not visible from street. no change to extg egress. no structural changes… | $14,000 |
| [202001162040](https://www.permitgraph.org/p/202001162040) | Jan 16, 2020 | Completed: final sign-off Mar 2022 | [601 Jackson St](https://www.permitgraph.org/a/0194/001) | [San Francisco Fire Protection](https://www.permitgraph.org/contractor/san-francisco-fire-protection-806216) | ref pa# 200410045809; like for like for (e) fire alar system all (e) intiating devices to be replaced, new monitoring mocules to be installed to tie in waterflow and tamper switch, all other devices… | $400 |
| [201404163384](https://www.permitgraph.org/p/201404163384) | Apr 16, 2014 | Never finaled: issued Apr 2014, no final | [601 Jackson St](https://www.permitgraph.org/a/0194/001) | [All Bay Construction Inc](https://www.permitgraph.org/contractor/all-bay-construction-inc-940952) | install interior non load bearing partition (sheet rock) on 2nd floor. | $6,500 |
| [201402269351](https://www.permitgraph.org/p/201402269351) | Feb 26, 2014 | Expired or cancelled: cancelled Jan 2026 | [601 Jackson St](https://www.permitgraph.org/a/0194/001) | [Western Builders](https://www.permitgraph.org/contractor/western-builders-428542) | at lobby entrance install pre-fabricated steel gate and railing (c0mpliance with maher ordinance no.155-13 not required. excavation less than 50 cu. yd.) | $2,000 |
| [200803177252](https://www.permitgraph.org/p/200803177252) | Mar 17, 2008 | Completed: final sign-off May 2008 | [601 Jackson St](https://www.permitgraph.org/a/0194/001) |  | erect a wall, non-electric, non illuminated, single faced new sign |  |
| [200609182542](https://www.permitgraph.org/p/200609182542) | Sep 18, 2006 | Completed: final sign-off Oct 2006 | [601 Jackson St](https://www.permitgraph.org/a/0194/001) | [W & J Plumbing Co.](https://www.permitgraph.org/contractor/w-j-plumbing-co-486546) | penthouse floor only remove portion of existing wall in between - stairway & elevator lobby @ penthouse floor. add a new 1 hour rated door &hallway exit to roof level.separate from existing office ar… | $3,500 |
| [200606275203](https://www.permitgraph.org/p/200606275203) | Jun 27, 2006 | Never finaled: issued Jun 2006, no final | [601 Jackson St](https://www.permitgraph.org/a/0194/001) | [San Francisco Fire Protection](https://www.permitgraph.org/contractor/san-francisco-fire-protection-806216) | move one strobe/horn on 3rd floor due to construct of 3 offices | $200 |
| [200602245349](https://www.permitgraph.org/p/200602245349) | Feb 24, 2006 | Never finaled: issued Feb 2006, no final | [601 Jackson St](https://www.permitgraph.org/a/0194/001) |  | remodel extg office space and install new airconditioning system per plan(see attatched sheet for reference) | $23,000 |
| [200602104401](https://www.permitgraph.org/p/200602104401) | Feb 10, 2006 | Completed: final sign-off Feb 2006 | [601 Jackson St](https://www.permitgraph.org/a/0194/001) | [D & S Leong Associates](https://www.permitgraph.org/contractor/d-s-leong-associates-618294) | relocate extg sprinklers heads and install 3 additional heads connect to exgt/replace upright heads to recessed pendent heads | $1,500 |
| [M35579](https://www.permitgraph.org/p/M35579) | Dec 5, 2005 | Never finaled: issued Dec 2005, no final | [601 Jackson St](https://www.permitgraph.org/a/0194/001) |  | street space |  |
| [200511077550](https://www.permitgraph.org/p/200511077550) | Nov 7, 2005 | Never finaled: issued Dec 2005, no final | [601 Jackson St](https://www.permitgraph.org/a/0194/001) |  | enclose penthouse floor opening approximate 7'x9'. | $15,000 |
| [200509304423](https://www.permitgraph.org/p/200509304423) | Sep 30, 2005 | Completed: final sign-off Feb 2006 | [601 Jackson St](https://www.permitgraph.org/a/0194/001) |  | tenant improvement at 3rd floor/add floor tiles suspension ceiling/ceiling light and kchn/add door from elevator lobby to exit stairway | $60,000 |
| [200506215599](https://www.permitgraph.org/p/200506215599) | Jun 21, 2005 | Completed: final sign-off Jul 2005 | [601 Jackson St](https://www.permitgraph.org/a/0194/001) | [Transworld Construction](https://www.permitgraph.org/contractor/transworld-construction-371269) | to renew 200502256241 for final inspection |  |
| [200503046841](https://www.permitgraph.org/p/200503046841) | Mar 4, 2005 | Completed: final sign-off Jul 2005 | [851 Kearny St](https://www.permitgraph.org/a/0194/001) | [Transworld Construction](https://www.permitgraph.org/contractor/transworld-construction-371269) | renew 200111213751, 200207020550, 9506166 for final insp. |  |
| [200502256241](https://www.permitgraph.org/p/200502256241) | Feb 25, 2005 | Expired or cancelled: expired Jul 2005 | [601 Jackson St](https://www.permitgraph.org/a/0194/001) | [Transworld Construction](https://www.permitgraph.org/contractor/transworld-construction-371269) | renew app 9506166 for final inspection |  |
| [200410045809](https://www.permitgraph.org/p/200410045809) | Oct 4, 2004 | Completed: final sign-off Dec 2005 | [601 Jackson St](https://www.permitgraph.org/a/0194/001) | [San Francisco Fire Protection](https://www.permitgraph.org/contractor/san-francisco-fire-protection-806216) | install fire alarm system to new building | $10,000 |
| [200406025383](https://www.permitgraph.org/p/200406025383) | Jun 2, 2004 | Completed: final sign-off Mar 2005 | [601 Jackson St](https://www.permitgraph.org/a/0194/001) |  | rev.appl#9506166 change brick veneer installation detail from cement plaster backing to metal clad |  |
| [200310097081](https://www.permitgraph.org/p/200310097081) | Oct 9, 2003 | Completed: final sign-off Dec 2005 | [601 Jackson St](https://www.permitgraph.org/a/0194/001) | [Transworld Construction](https://www.permitgraph.org/contractor/transworld-construction-371269) | construct conc. block wall @kearny st.sidwalk for transofmer below sidewlak, to raise floor above | $3,000 |
| [200307290676](https://www.permitgraph.org/p/200307290676) | Jul 29, 2003 | Completed: final sign-off Dec 2005 | [601 Jackson St](https://www.permitgraph.org/a/0194/001) | [Perfect Connection Inc.](https://www.permitgraph.org/contractor/perfect-connection-inc-812380) | install fire sprinkler system. | $48,000 |
| [200207020550](https://www.permitgraph.org/p/200207020550) | Jul 2, 2002 | Completed: final sign-off Dec 2005 | [851 Kearny St](https://www.permitgraph.org/a/0194/001) | [Transworld Construction](https://www.permitgraph.org/contractor/transworld-construction-371269) | revision to 200111213751 to providee shoring along east (kearny st) & north (jackson st) | $100 |
| [200111213751](https://www.permitgraph.org/p/200111213751) | Nov 21, 2001 | Completed: final sign-off Dec 2005 | [851 Kearny St](https://www.permitgraph.org/a/0194/001) |  | shoring along east (kearny) & north (jackson st)prop lines for new 4 story build on vacant lot | $80,000 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Transworld Construction](https://www.permitgraph.org/contractor/transworld-construction-371269) (5), [San Francisco Fire Protection](https://www.permitgraph.org/contractor/san-francisco-fire-protection-806216) (3), [All Bay Construction Inc](https://www.permitgraph.org/contractor/all-bay-construction-inc-940952), [D & S Leong Associates](https://www.permitgraph.org/contractor/d-s-leong-associates-618294), [Paradise Construction](https://www.permitgraph.org/contractor/paradise-construction-1101815), [Perfect Connection Inc.](https://www.permitgraph.org/contractor/perfect-connection-inc-812380), [W & J Plumbing Co.](https://www.permitgraph.org/contractor/w-j-plumbing-co-486546), [Western Builders](https://www.permitgraph.org/contractor/western-builders-428542)
- Architects: [Kung Kay Chiu](https://www.permitgraph.org/professional/kung-kay-chiu-C24622), [Kwan And Assoc.](https://www.permitgraph.org/professional/kwan-and-assoc-S1836), [Lisa Wong](https://www.permitgraph.org/professional/lisa-wong-C17301)
- Engineers: [Albert Urrutia](https://www.permitgraph.org/professional/albert-urrutia-S2994), [Lok C. Kwan](https://www.permitgraph.org/professional/lok-c-kwan-S1836)
- Authorized agents: [Helen Lam](https://www.permitgraph.org/professional/helen-lam-S1836)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.