# 288 Pacific Av

Block 0166, lot 003. Page: https://www.permitgraph.org/a/0166/003

The city's assessor roll has no record for this parcel.

## Permits filed here

12 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [201812128114](https://www.permitgraph.org/p/201812128114) | Dec 12, 2018 | Never finaled: issued Dec 2018, no final | [288 Pacific Av](https://www.permitgraph.org/a/0166/003) |  | 7th floor ph-c: installing wall in bedroom for closet cabinets with removable shelves. | $1,500 |
| [201804106005](https://www.permitgraph.org/p/201804106005) | Apr 10, 2018 | Never finaled: issued Apr 2018, no final | [240 Pacific Av](https://www.permitgraph.org/a/0166/003) | [Swinerton Builders](https://www.permitgraph.org/contractor/swinerton-builders-92) | revision to 201508134190 s/3 to update latest glazing performance per nfrc certificates & revise t-24 reports |  |
| [201802121068](https://www.permitgraph.org/p/201802121068) | Feb 12, 2018 | Never finaled: issued Feb 2018, no final | [240 Pacific Av](https://www.permitgraph.org/a/0166/003) | [Swinerton Builders](https://www.permitgraph.org/contractor/swinerton-builders-92) | as built underground for fire water. ref 201609228580. revision includes suspended in bldg riser, added flex tend fitting, revised back fill material in trench drain maher not req |  |
| [201712217040](https://www.permitgraph.org/p/201712217040) | Dec 21, 2017 | Never finaled: issued Jan 2018, no final | [288 Pacific Av](https://www.permitgraph.org/a/0166/003) | [Priority Architectural Graphics Dba Prio](https://www.permitgraph.org/contractor/priority-architectural-graphics-dba-prio-763170) | (31) evacuation maps to be reviewed by sffd. floors 1, 2 , 3, 4, 5, 6, 7. maher na. ref pa 201508134190. n/a for maher. | $5,000 |
| [M842847](https://www.permitgraph.org/p/M842847) | Oct 11, 2017 | Never finaled: issued Oct 2017, no final | [240 Pacific Av](https://www.permitgraph.org/a/0166/003) |  | street space w/mta |  |
| [201707141956](https://www.permitgraph.org/p/201707141956) | Jul 14, 2017 | Never finaled: issued Jul 2017, no final | [240 Pacific Av](https://www.permitgraph.org/a/0166/003) | [Swinerton Builders](https://www.permitgraph.org/contractor/swinerton-builders-92) | revision to addendum #3 pa #201508134190. fir exterior fire stopping detail at slab edge. |  |
| [M770987](https://www.permitgraph.org/p/M770987) | Mar 23, 2017 | Never finaled: issued Mar 2017, no final | [240 Pacific Av](https://www.permitgraph.org/a/0166/003) |  | street space permit - renewal of permit #201508134190 |  |
| [201702139302](https://www.permitgraph.org/p/201702139302) | Feb 13, 2017 | Never finaled: issued Mar 2017, no final | [240 Pacific Av](https://www.permitgraph.org/a/0166/003) | [Swinerton Builders](https://www.permitgraph.org/contractor/swinerton-builders-92) | tower crane installation in northeast corner or site, manitowoc potain mdt 219-j10. reference to building application no. 201508134190. maher not req | $650,000 |
| [201612144923](https://www.permitgraph.org/p/201612144923) | Dec 14, 2016 | Completed: final sign-off Mar 2018 | [240 Pacific Av](https://www.permitgraph.org/a/0166/003) | [Swinerton Builders](https://www.permitgraph.org/contractor/swinerton-builders-92) | temporary shoring and excavation | $250,000 |
| [M743387](https://www.permitgraph.org/p/M743387) | Dec 2, 2016 | Never finaled: issued Dec 2016, no final | [284 Pacific Av](https://www.permitgraph.org/a/0166/003) |  | per pa #201508134190, add address to block 0166, lot 003 as; 284, 286(commercial), 288 pacific ave(residential) |  |
| [201609228580](https://www.permitgraph.org/p/201609228580) | Sep 22, 2016 | Never finaled: issued Sep 2016, no final | [240 Pacific Av](https://www.permitgraph.org/a/0166/003) | [Superior Automatic Sprinkler](https://www.permitgraph.org/contractor/superior-automatic-sprinkler-287121), [Swinerton Builders](https://www.permitgraph.org/contractor/swinerton-builders-92) | fire water installation of 8" service off (e) 12" main | $10,000 |
| [201508134190](https://www.permitgraph.org/p/201508134190) | Aug 13, 2015 | Completed: final sign-off Jul 2018 | [240 Pacific Av](https://www.permitgraph.org/a/0166/003) | [Swinerton Builders](https://www.permitgraph.org/contractor/swinerton-builders-92) | site permit: to erect 7 stories, 1 basement, 33 units residential, retail, parking & lobby. ** maher: compliance with ordinance no# 155-13 required; route to dph ** | $21,300,000 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Swinerton Builders](https://www.permitgraph.org/contractor/swinerton-builders-92) (7), [Priority Architectural Graphics Dba Prio](https://www.permitgraph.org/contractor/priority-architectural-graphics-dba-prio-763170), [Superior Automatic Sprinkler](https://www.permitgraph.org/contractor/superior-automatic-sprinkler-287121)
- Architects: [Glenn G. Rescalvo](https://www.permitgraph.org/professional/glenn-g-rescalvo-C27080) (2), [Stephen Mccullough](https://www.permitgraph.org/professional/stephen-mccullough-C66618)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/a/0166/003.